8026 S WESTLAWN AVE 90045

Certificate Information: 8026 S WESTLAWN AVE 90045

Application / Permit
23014-10000-04389
Plan Check / Job No.
B23LA20236
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. GROUND FLOOR ADDITION TO (E) 1-STORY SFD WITH INTERIOR STR. REMODEL
Permit Issued
Issued on 4/25/2024
Issuing Office
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 VIVIAN LAO
Corrections Issued 11/9/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 11/22/2023 TU HUA
Applicant returned to address corrections 4/11/2024 VIVIAN LAO
Plan Check Approved 4/18/2024 VIVIAN LAO
Issued 4/25/2024 APPLICANT
CofO in Progress 3/5/2026 JESUS PINEDA
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/21/2024 DARIN LAM
Roof/Waste drainage to street Cleared 2/21/2024 DARIN LAM
Sewer availability Cleared 2/21/2024 DARIN LAM
Specific Plan Cleared 2/28/2024 FREDDY GARCIA

Contact Information

Contractor Yarden Builders Inc; Lic. No.: 952977-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: NA26962       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 5/15/2024 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 5/17/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Corrections Issued JESUS PINEDA
Deputy Wood Construction 7/10/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 7/10/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 7/10/2024 Approved BOBBY KEY
ELECTRICAL-Rough 7/12/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 7/16/2024 Approved BOBBY KEY
Final 7/16/2024 Corrections Issued BOBBY KEY
Green Building Rough 7/16/2024 Approved BOBBY KEY
HVAC-Rough 7/16/2024 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 7/16/2024 Partial Approval BOBBY KEY
HVAC-Rough 7/24/2024 Approved BOBBY KEY
Insulation 7/24/2024 Corrections Issued BOBBY KEY
Insulation 7/29/2024 Approved BOBBY KEY
Drywall Nailing 8/6/2024 Approved BOBBY KEY
ELECTRICAL-Final 11/5/2024 Corrections Issued TEMISTOCLES CAAL
Final 11/5/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 11/5/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/5/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 11/5/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 11/5/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 11/20/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 11/20/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/20/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 12/12/2024 Approved TEMISTOCLES CAAL
Final 12/12/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 12/12/2024 Approved TEMISTOCLES CAAL
HVAC-Final 12/12/2024 Approved TEMISTOCLES CAAL
Final 3/5/2026 OK to Issue CofO JESUS PINEDA