16699 W MORRISON ST 91436

Certificate Information: 16699 W MORRISON ST 91436

Application / Permit
23014-10000-04360
Plan Check / Job No.
B23LA20057
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING RUMPUS ROOM INTO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND REMOVE ATTACHED BREEZWAY - PER DESIGN
Permit Issued
Issued on 2/15/2024
Issuing Office
Current Status
CofO Issued on 6/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 DANIEL ABRAMYAN
Corrections Issued 10/30/2023 DANIEL ABRAMYAN
Plan Check Approved 2/2/2024 ALEC MOUSAKHANIAN
Issued 2/15/2024 APPLICANT
CofO in Progress 5/29/2025 JOHN COLEMAN
Permit Finaled 6/18/2025 JOHN JANSON
CofO Issued 6/18/2025 JOHN JANSON
Permit Finaled 6/18/2025 JOHN JANSON

Permit Application Clearance Information

Hold Cleared 1/23/2024 MARIA VENDIVIL
Address approval Cleared 1/30/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/30/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/30/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/30/2024 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 2/2/2024 ALEC MOUSAKHANIAN

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/26/2024 No Access for Inspection VINCENT HANLEY
Drywall Nailing 4/26/2024 No Access for Inspection VINCENT HANLEY
Final 4/26/2024 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 4/26/2024 No Access for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 4/26/2024 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 9/6/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 10/15/2024 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/27/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/12/2024 Approved THOMAS FINNILA
Footing/Foundation/Slab 12/12/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 12/12/2024 Approved THOMAS FINNILA
Footing/Foundation/Slab 12/20/2024 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/24/2024 Approved JEFFREY HARTLINE
HVAC-Rough 12/24/2024 Approved JEFFREY HARTLINE
Insulation 12/27/2024 Corrections Issued THOMAS FINNILA
Drywall Nailing 1/7/2025 Approved JOHN COLEMAN
Final 2/28/2025 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 2/28/2025 Approved JOHN COLEMAN
HVAC-Final 2/28/2025 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Final 2/28/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved JOHN COLEMAN
Service/Power Release 2/28/2025 Approved JOHN COLEMAN
Smoke Detectors 2/28/2025 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Final 3/7/2025 Not Ready for Inspection THOMAS FINNILA
Final 3/7/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 3/7/2025 Approved THOMAS FINNILA
Smoke Detectors 3/7/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 3/18/2025 Not Ready for Inspection JOHN COLEMAN
Final 3/18/2025 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Final 3/18/2025 Approved JOHN COLEMAN
Service/Power Release 3/18/2025 Approved JOHN COLEMAN
ELECTRICAL-Final 4/2/2025 Approved JOHN COLEMAN
Final 4/2/2025 Partial Inspection JOHN COLEMAN
Final 5/29/2025 OK to Issue CofO JOHN COLEMAN