1580 S WESTHOLME AVE 90024

Certificate Information: 1580 S WESTHOLME AVE 90024

Application / Permit
23014-10000-04351
Plan Check / Job No.
B23LA20017
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND (N) ADDITION WITH ROOF DECK TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERING.
Permit Issued
Issued on 5/8/2024
Issuing Office
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 10/30/2023 ISIS ARGUETA
Corrections Issued 10/31/2023 ISIS ARGUETA
Applicant returned to address corrections 12/20/2023 ISIS ARGUETA
Applicant returned to address corrections 1/19/2024 KAMYAR EMAMI
Applicant returned to address corrections 3/13/2024 KAMYAR EMAMI
Plan Check Approved 3/22/2024 KAMYAR EMAMI
Issued 5/8/2024 APPLICANT
CofO in Progress 1/27/2026 MICHAEL ALLEN
Permit Finaled 1/30/2026 RICHARD STEINBACH
Permit Finaled 1/30/2026 RICHARD STEINBACH
CofO Issued 1/30/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/6/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 11/6/2023 DARIN LAM
Sewer availability Cleared 11/6/2023 DARIN LAM
Grading Pre-Inspection Cleared 11/7/2023 ROBERT HUGHES
Specific Plan Cleared 12/15/2023 JOSHUA JONES
Roof/Waste drainage to street Cleared 12/21/2023 DARIN LAM

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B       ,
Engineer Dumack,, Heath Alan; Lic. No.: C60391 PO BOX 487      PENNS PARK, PA 18943
Engineer Salto,, Alvaro; Lic. No.: NA83859       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/30/2024 Conditional Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 6/3/2024 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 6/21/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 6/21/2024 Partial Approval KIRK SANDERS
METHANE-Barrier 6/21/2024 Approved KIRK SANDERS
METHANE-Subgrade 6/21/2024 Approved KIRK SANDERS
ELECTRICAL-Rough 8/8/2024 No Access for Inspection CHRISTOPHER WILSON
HVAC-Rough 8/8/2024 No Access for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 8/8/2024 No Access for Inspection CHRISTOPHER WILSON
Wood Frame 8/8/2024 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/12/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 8/12/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 8/12/2024 Corrections Issued ASHLEY THOMPSON
Special/Order Compliance 8/12/2024 Partial Inspection REGINA MENDEZ
BUILDING-Rough-Frame 8/16/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/16/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved KIRK SANDERS
Shower Pan 8/16/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 8/29/2024 Approved KIRK SANDERS
ELECTRICAL-Rough 8/29/2024 Approved KIRK SANDERS
Green Building Rough 8/29/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 8/29/2024 Approved KIRK SANDERS
METHANE-Rough 8/29/2024 Approved KIRK SANDERS
PLUMBING-Rough 8/29/2024 Approved KIRK SANDERS
Insulation 9/4/2024 Corrections Issued KIRK SANDERS
Insulation 9/6/2024 No Access for Inspection KIRK SANDERS
Insulation 9/11/2024 Approved ARAM AVEDISIAN
Drywall Nailing 9/18/2024 Approved KIRK SANDERS
Underground Mechanical 1/15/2025 Partial Approval KIRK SANDERS
Sewer 1/16/2025 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 2/7/2025 Approved JESUS RODRIGUEZ
Sewer 4/10/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 6/17/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Not Ready KIRK SANDERS
ELECTRICAL-Final 6/18/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Final 6/18/2025 Not Ready for Inspection TEMISTOCLES CAAL
Service/Power Release 6/18/2025 Not Ready for Inspection TEMISTOCLES CAAL
Sewer 6/18/2025 Not Ready for Inspection TEMISTOCLES CAAL
Smoke Detectors 6/18/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 7/17/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 7/17/2025 Corrections Issued DANIEL VERA
Service/Power Release 7/17/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 7/24/2025 Approved ARAM AVEDISIAN
HVAC-Final 7/24/2025 Approved ARAM AVEDISIAN
Service/Power Release 7/24/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 7/30/2025 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 7/30/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 9/2/2025 No Access for Inspection DANIEL VERA
Service/Power Release 9/2/2025 No Access for Inspection DANIEL VERA
Service/Power Release 10/6/2025 Corrections Issued MICHAEL ALLEN
Final 10/21/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 10/21/2025 Approved MICHAEL ALLEN
PLUMBING-Final 10/21/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready MICHAEL ALLEN
Service/Power Release 10/21/2025 Approved MICHAEL ALLEN
Final 11/3/2025 Corrections Issued MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved MICHAEL ALLEN
Service/Power Release 11/3/2025 Approved MICHAEL ALLEN
Final 1/26/2026 OK to Issue CofO MICHAEL ALLEN
Service/Power Release 1/26/2026 Approved MICHAEL ALLEN
Sewer 1/26/2026 Approved MICHAEL ALLEN