2053 W 79TH ST 90047

Certificate Information: 2053 W 79TH ST 90047

Application / Permit
23014-10000-04323
Plan Check / Job No.
B23LA19871
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD
Permit Issued
Issued on 11/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2023 APPLICANT
Assigned to Plan Check Engineer 10/20/2023 VICTOR CHEN
Corrections Issued 10/20/2023 VICTOR CHEN
Plan Check Approved 11/28/2023 FERNANDO FLORES
Issued 11/28/2023 APPLICANT
CofO in Progress 10/2/2024 JOSE MACIAS
CofO Issued 10/15/2024 RUBEN SALAS
Permit Finaled 10/15/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/19/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 11/28/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/9/2024 Corrections Issued ENRIQUE MIRELES
Deputy Drilled-In Anchors 1/18/2024 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 1/29/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 2/28/2024 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 3/4/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 3/11/2024 Approved JOSE MACIAS
Wood Frame 3/19/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 4/19/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 4/19/2024 Corrections Issued JOSE MACIAS
Green Building Rough 4/19/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 4/19/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 4/24/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 4/24/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 5/20/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 5/20/2024 Approved JOSE MACIAS
Green Building Rough 5/20/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 5/20/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 6/4/2024 Approved JOSE MACIAS
Insulation 6/4/2024 Approved JOSE MACIAS
Drywall Nailing 6/12/2024 Approved JOSE MACIAS
Shower Pan 6/27/2024 Corrections Issued JOSE MACIAS
Shower Pan 7/3/2024 No Access for Inspection CRAIG DAVIS
Shower Pan 7/5/2024 Approved JOSE MACIAS
Final 9/24/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 9/24/2024 Approved AMIR NAZARIAN
Smoke Detectors 9/24/2024 Corrections Issued AMIR NAZARIAN
Final 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 9/27/2024 Approved AMIR NAZARIAN
Final 10/1/2024 OK to Issue CofO JOSE MACIAS
Interior/Exterior Lathing 10/1/2024 Approved JOSE MACIAS