2053 W 79TH ST 90047
Certificate Information: 2053 W 79TH ST 90047
- Application / Permit
- 23014-10000-04323
- Plan Check / Job No.
- B23LA19871
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2023 | VICTOR CHEN |
| Corrections Issued | 10/20/2023 | VICTOR CHEN |
| Plan Check Approved | 11/28/2023 | FERNANDO FLORES |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 10/2/2024 | JOSE MACIAS |
| CofO Issued | 10/15/2024 | RUBEN SALAS |
| Permit Finaled | 10/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/19/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2024 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 1/18/2024 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 1/29/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 3/4/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/11/2024 | Approved | JOSE MACIAS |
| Wood Frame | 3/19/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/19/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 4/19/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 4/19/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 4/19/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 4/24/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 4/24/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/20/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 5/20/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 6/4/2024 | Approved | JOSE MACIAS |
| Insulation | 6/4/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 6/12/2024 | Approved | JOSE MACIAS |
| Shower Pan | 6/27/2024 | Corrections Issued | JOSE MACIAS |
| Shower Pan | 7/3/2024 | No Access for Inspection | CRAIG DAVIS |
| Shower Pan | 7/5/2024 | Approved | JOSE MACIAS |
| Final | 9/24/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 9/24/2024 | Approved | AMIR NAZARIAN |
| Smoke Detectors | 9/24/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 9/27/2024 | Approved | AMIR NAZARIAN |
| Final | 10/1/2024 | OK to Issue CofO | JOSE MACIAS |
| Interior/Exterior Lathing | 10/1/2024 | Approved | JOSE MACIAS |