106 S CITRUS AVE 90036

Certificate Information: 106 S CITRUS AVE 90036

Application / Permit
23014-10000-04317
Plan Check / Job No.
B23LA19841
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ENCLOSE AND CONVERT AREA UNDER 2ND FLOOR OVERHANG TO HABITABLE SPACE. NO INCREASE IN FLOOR AREA.
Permit Issued
Issued on 5/28/2024
Issuing Office
Current Status
Issued on 5/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 DANIEL YIP
Corrections Issued 10/28/2023 DANIEL YIP
Quality Review Completed 10/31/2023 PRANITA SHAH
Applicant returned to address corrections 4/24/2024 DANIEL YIP
Plan Check Approved 5/10/2024 DANIEL YIP
Issued 5/28/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/25/2024 Partial Inspection RONNIE MINDANAO
Footing/Foundation/Slab 6/25/2024 Partial Inspection RONNIE MINDANAO
METHANE-Barrier 6/25/2024 Partial Inspection RONNIE MINDANAO
METHANE-Subgrade 6/25/2024 Partial Inspection RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 8/26/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 8/26/2024 Approved RONNIE MINDANAO
METHANE-Barrier 8/26/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 8/26/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Conditional Approval RONNIE MINDANAO
Green Building Rough 11/22/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 11/22/2024 Approved RONNIE MINDANAO
Deputy Wood Construction 11/26/2024 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 11/27/2024 Approved RONNIE MINDANAO
Green Building Rough 11/27/2024 Not Ready for Inspection RONNIE MINDANAO
Drywall Nailing 12/6/2024 Approved RONNIE MINDANAO
Green Building Rough 12/6/2024 Approved RONNIE MINDANAO
Insulation 12/6/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 12/16/2024 Approved JEFFREY MEAD
Final 8/22/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 8/22/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 8/22/2025 Corrections Issued RONNIE MINDANAO