775-777 N SARBONNE ROAD 90077
Certificate Information: 775-777 N SARBONNE ROAD 90077
- Application / Permit
- 23014-10000-04302
- Plan Check / Job No.
- B23LA19734
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel to existing single family dwelling and addition for new attached adu
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- Issued on 5/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | CARLOS MONTES |
| Corrections Issued | 10/31/2023 | CARLOS MONTES |
| Quality Review Completed | 10/31/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/4/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 11/5/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 12/19/2024 | CARLOS MONTES |
| Plan Check Approved | 5/23/2025 | CARLOS MONTES |
| No Progress | 5/23/2025 | CARLOS MONTES |
| Plan Check Approved | 5/28/2025 | CARLOS MONTES |
| Issued | 5/28/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/7/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/7/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/7/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/7/2023 | DINAH GARIN |
| Sewer availability | Cleared | 11/7/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/20/2023 | DINAH GARIN |
| Distance to fire station | Cleared | 12/15/2023 | RUEL COLE |
| Hydrant and Access approval | Cleared | 12/15/2023 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 3/28/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/11/2025 | VLADIMIR ARUTYUNYAN |
| Building over 36-ft | Cleared | 5/23/2025 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/23/2025 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/23/2025 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 5/23/2025 | CARLOS MONTES |
| Address approval | Cleared | 5/27/2025 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Larkin,, Dean A; Lic. No.: C28277 | 8912 HOLLYWOOD HILLS RD LOS ANGELES, CA 90046 |
| Contractor | Tyler Development Corporation; Lic. No.: 451882-B | , |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 9/30/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 10/21/2025 | Conditional Approval | DAVID FEILER |
| PLUMBING-Rough | 11/10/2025 | Corrections Issued | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 12/3/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 2/25/2026 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/27/2026 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/17/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/17/2026 | Partial Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 5/21/2026 | Partial Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 6/4/2026 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 6/10/2026 | Conditional Approval | ANDREW NAVE |