3670 N AMESBURY ROAD 90027
Certificate Information: 3670 N AMESBURY ROAD 90027
- Application / Permit
- 23014-10000-04293
- Plan Check / Job No.
- B23LA19683
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 2-STORY SFD WITH BASEMENT AND REMODEL.
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2023 | APPLICANT |
| Assigned to Zoning Architect | 10/26/2023 | JASON BRAVO |
| Assigned to Plan Check Engineer | 11/2/2023 | VIVIAN LAO |
| Corrections Issued | 11/9/2023 | VIVIAN LAO |
| Quality Review Completed | 11/17/2023 | KEN GILL |
| Building Plans Picked Up | 11/20/2023 | APPLICANT |
| Applicant returned to address corrections | 1/23/2024 | VIVIAN LAO |
| Plan Check Approved | 2/27/2024 | VIVIAN LAO |
| Issued | 2/27/2024 | APPLICANT |
| CofO in Progress | 12/11/2025 | ENRIQUE MIRELES |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
| CofO Issued | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/23/2024 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 1/23/2024 | VIVIAN LAO |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 2/23/2024 | ANTHONY TRAN |
Contact Information
| Contractor | Vertex Construction & Design; Lic. No.: 722885-B | 4858 FOUNTAIN AVENUE LOS ANGELES, CA 90029 |
| Engineer | Tsai,, Willy Y; Lic. No.: C35589 | 1545 RUBIO DR SAN MARINO, CA 91108 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2024 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/22/2024 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/22/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/22/2024 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/26/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/1/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 7/1/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/8/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/8/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Gas Test | 8/30/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/11/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 10/11/2024 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/11/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/21/2024 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 10/23/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/23/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/23/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 10/28/2024 | Approved | ENRIQUE MIRELES |
| Deck | 1/6/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/6/2025 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/12/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/30/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 11/12/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/17/2025 | Corrections Issued | ENRIQUE MIRELES |
| Final | 11/19/2025 | OK to Issue CofO | ENRIQUE MIRELES |