2720 N GLENDOWER AVE 90027
Certificate Information: 2720 N GLENDOWER AVE 90027
- Application / Permit
- 23014-10000-04256
- Plan Check / Job No.
- B23LA19512
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL, 2-STORY AND CARPORT ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | DANIEL YIP |
| Corrections Issued | 11/16/2023 | DANIEL YIP |
| Quality Review Completed | 11/17/2023 | KEN GILL |
| Building Plans Picked Up | 11/27/2023 | APPLICANT |
| Applicant returned to address corrections | 12/18/2023 | DANIEL YIP |
| Applicant returned to address corrections | 1/17/2024 | DANIEL YIP |
| Plan Check Approved | 1/29/2024 | DANIEL YIP |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 9/15/2025 | ENRIQUE MIRELES |
| Permit Finaled | 9/16/2025 | DEROLD HAUFF |
| CofO Issued | 9/16/2025 | DEROLD HAUFF |
| Permit Finaled | 9/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/15/2023 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/21/2023 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 1/3/2024 | DAVID VO |
| BHO/Hillside ordinance | Cleared | 1/3/2024 | DAVID VO |
| BHO/Hillside ordinance | Cleared | 1/3/2024 | DAVID VO |
| GPI Written Notices | Cleared | 1/4/2024 | ALEXANDER HELFER |
| Low Impact Development (LID) | Cleared | 1/6/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/11/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 1/26/2024 | JOHN CONNEALLY |
Contact Information
| Contractor | Level Frame Construction Inc; Lic. No.: 1078493-B | 5401 WEST ADAMS BLVD LOS ANGELES, CA 90016 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2024 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 5/9/2024 | Conditional Approval | ADAM BURGESS |
| Excavation/Setback/Form/Re-Bar | 5/13/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/13/2024 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 5/14/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/30/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/26/2024 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/25/2024 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 9/17/2024 | Approved | ENRIQUE MIRELES |
| Gas Test | 11/1/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/1/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/4/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/15/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/18/2024 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 11/18/2024 | Approved | JEFFREY MEAD |
| Insulation | 11/22/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 11/26/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 12/9/2024 | Approved | ENRIQUE MIRELES |
| Shower Pan | 12/16/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/23/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/7/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/17/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 7/18/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/30/2025 | Approved | BRENDAN MORELLI |
| Final | 8/29/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/29/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/29/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/5/2025 | OK to Issue CofO | ENRIQUE MIRELES |