334 S BURLINGAME AVE 90049

Certificate Information: 334 S BURLINGAME AVE 90049

Application / Permit
23014-10000-04242
Plan Check / Job No.
B23LA19056
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ADDITION TO (E) RECROOM
Permit Issued
Issued on 4/11/2024
Issuing Office
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 CARLOS MONTES
Corrections Issued 10/16/2023 CARLOS MONTES
Quality Review Completed 10/16/2023 GARO TELMI
Applicant returned to address corrections 1/31/2024 CARLOS MONTES
Plan Check Approved 4/1/2024 CARLOS MONTES
Issued 4/11/2024 APPLICANT
CofO in Progress 3/10/2026 HERBERT GIRON
Permit Finaled 3/16/2026 RICHARD STEINBACH
CofO Issued 3/16/2026 RICHARD STEINBACH
Permit Finaled 3/16/2026 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 12/22/2023 ROGELIO CORTES
GPI Written Notices Cleared 1/31/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 1/31/2024 CARLOS MONTES
Specific Plan Cleared 3/18/2024 MOHAMMAD HASAN
Eng Process Fee Ord 176,300 Cleared 3/19/2024 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 3/19/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 3/19/2024 VLADIMIR ARUTYUNYAN
Tract Map conditions Cleared 3/20/2024 DANIEL CORONADO
ZA Case Cleared 3/20/2024 DANIEL CORONADO
ZA Case Cleared 3/20/2024 DANIEL CORONADO

Contact Information

Architect Holz,, Michael B; Lic. No.: C28082 12548 EVERGLADE STREET      LOS ANGELES, CA 90066
Contractor M G Partners Inc; Lic. No.: 886387-B 761 E DAILY DR #140      CAMARILLO, CA 93010
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/8/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 7/29/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 8/12/2024 Partial Approval ARAM AVEDISIAN
Underground Mechanical 8/12/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/21/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 3/4/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 3/4/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/4/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/7/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 5/7/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 6/25/2025 Conditional Approval HERBERT GIRON
Green Building Rough 6/25/2025 Approved HERBERT GIRON
Insulation 6/25/2025 Approved HERBERT GIRON
Verify Sprinkler Sign Off 6/25/2025 Approved HERBERT GIRON
Drywall Nailing 7/21/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 7/30/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/3/2026 Corrections Issued HERBERT GIRON
Gas Test 2/3/2026 Approved HERBERT GIRON
HVAC-Final 2/3/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/3/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 2/12/2026 Approved HERBERT GIRON
HVAC-Final 2/12/2026 Approved HERBERT GIRON
PLUMBING-Final 2/12/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/9/2026 Approved HERBERT GIRON
Final 3/9/2026 OK to Issue CofO HERBERT GIRON
Footing/Foundation/Slab 3/9/2026 Approved HERBERT GIRON
Green Building Final 3/9/2026 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved HERBERT GIRON
Smoke Detectors 3/9/2026 Approved HERBERT GIRON