4856 E EDISON ST 90032

Certificate Information: 4856 E EDISON ST 90032

Application / Permit
23014-10000-04241
Plan Check / Job No.
B23LA19440
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD. CONVERT CARPORT TO GARAGE AND PORTION OF THAT TO SFD. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 5/6/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 ADRIANA LOPEZ
Corrections Issued 11/16/2023 ADRIANA LOPEZ
Quality Review Completed 11/17/2023 KEN GILL
Building Plans Picked Up 11/20/2023 APPLICANT
Applicant returned to address corrections 3/11/2024 ADRIANA LOPEZ
Applicant returned to address corrections 3/26/2024 ADRIANA LOPEZ
Applicant returned to address corrections 4/26/2024 ADRIANA LOPEZ
Plan Check Approved 5/2/2024 ADRIANA LOPEZ
Issued 5/6/2024 APPLICANT
CofO in Progress 11/6/2025 LILIANA PORTILLO
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/23/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/24/2024 JESSICA OPINION
Sewer availability Cleared 4/24/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 4/25/2024 CELINA MORENO
Highway dedication Cleared 4/25/2024 CELINA MORENO
GPI Written Notices Cleared 5/2/2024 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 5/2/2024 ADRIANA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mchantaf,, Kamal Beshara; Lic. No.: C51050 23315 SARATOGA SPRINGS PL      MURRIETA, CA 92562

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/9/2024 Partial Inspection LILIANA PORTILLO
Pre-Inspection 6/3/2024 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 7/9/2024 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 7/16/2024 Approved LILIANA PORTILLO
Footing/Foundation/Slab 7/16/2024 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 9/23/2024 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 9/23/2024 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 9/26/2024 Not Ready for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 9/26/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval BRENDAN MORELLI
Green Building Rough 9/26/2024 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 9/26/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 9/26/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 10/24/2024 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 10/24/2024 Corrections Issued LILIANA PORTILLO
Green Building Rough 10/24/2024 Approved LILIANA PORTILLO
HVAC-Rough 10/24/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/24/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/4/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 11/4/2024 Approved LILIANA PORTILLO
Green Building Rough 11/4/2024 Approved LILIANA PORTILLO
HVAC-Rough 11/4/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 11/4/2024 Approved LILIANA PORTILLO
Insulation 11/7/2024 Approved WILLIAM SIERRA
Drywall Nailing 11/13/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/13/2024 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 12/18/2024 Approved WILLIAM SIERRA
Shower Pan 12/18/2024 Corrections Issued WILLIAM SIERRA
Shower Pan 12/23/2024 Approved ANTHONY RAMOS
Service/Power Release 6/10/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 8/4/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/25/2025 Approved LILIANA PORTILLO
Service/Power Release 8/25/2025 Approved LILIANA PORTILLO
Final 10/29/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 10/29/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 10/29/2025 Approved LILIANA PORTILLO
Final 11/5/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 11/5/2025 Approved LILIANA PORTILLO
HVAC-Final 11/5/2025 Approved LILIANA PORTILLO
PLUMBING-Final 11/5/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved LILIANA PORTILLO