1023 1/2 W 22ND ST 90007
Certificate Information: 1023 1/2 W 22ND ST 90007
- Application / Permit
- 23014-10000-04237
- Plan Check / Job No.
- B23LA19399
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 story ADU ATTACHED TO EXISTING GARAGE. ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 3/19/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | SUNMIN LEE |
| Corrections Issued | 11/2/2023 | SUNMIN LEE |
| Quality Review Completed | 11/3/2023 | KEN GILL |
| Building Plans Picked Up | 11/6/2023 | APPLICANT |
| Applicant returned to address corrections | 1/10/2024 | SUNMIN LEE |
| Plan Check Approved | 2/23/2024 | SUNMIN LEE |
| Issued | 3/19/2024 | APPLICANT |
| CofO in Progress | 10/29/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/20/2023 | RYAN LY |
| Address approval | Cleared | 11/20/2023 | DAVID LOPEZ |
| CPC | Cleared | 11/20/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | DAVID LOPEZ |
| HPOZ | Cleared | 11/20/2023 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 11/20/2023 | MICAELA TORRES-GIL |
| Sewer availability | Cleared | 11/20/2023 | DAVID LOPEZ |
| ZI | Cleared | 11/20/2023 | MICAELA TORRES-GIL |
| ZI | Cleared | 11/20/2023 | RYAN LY |
| Low Impact Development (LID) | Cleared | 12/22/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Geologist | Siskowic,, John Gary; Lic. No.: GEO8255 | 515 S CATALINA AVE APT A REDONDO BEACH, CA 90277 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/29/2024 | Corrections Issued | BRENDAN MORELLI |
| METHANE-Barrier | 3/29/2024 | Approved | BRENDAN MORELLI |
| METHANE-Subgrade | 3/29/2024 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/8/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 4/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 4/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 4/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 4/22/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 5/8/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 5/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/28/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/5/2024 | Order to Comply Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 7/16/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/28/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/28/2024 | Approved | ALEJANDRO DE ARTOLA |