7919 W DAY ST 91040

Certificate Information: 7919 W DAY ST 91040

Application / Permit
23014-10000-04236
Plan Check / Job No.
B23LA19397
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Single-story ground floor addition to (E) SFD
Permit Issued
Issued on 11/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 GEORGE JOLAKIAN
Corrections Issued 10/26/2023 GEORGE JOLAKIAN
Quality Review Completed 10/27/2023 KEN GILL
Building Plans Picked Up 10/30/2023 APPLICANT
Plan Check Approved 11/9/2023 GEORGE JOLAKIAN
Issued 11/14/2023 APPLICANT
CofO in Progress 9/5/2024 DAVID ANDERSON
CofO Issued 9/23/2024 DANIEL ORRANTE
Permit Finaled 9/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/31/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/31/2023 LEE GUILBEAUX
Watercourse Cleared 10/31/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/9/2023 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Basso,, Alexandre; Lic. No.: C77670 151 S EL MOLINA AVE STE 202      PASADENA, CA 91101

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/15/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 11/20/2023 Approved DAVID ANDERSON
Footing/Foundation/Slab 11/20/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Corrections Issued THOMAS FINNILA
Insulation 12/5/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/5/2023 Partial Approval THOMAS FINNILA
Insulation 12/6/2023 Partial Approval DAVID ANDERSON
PLUMBING-Rough 12/6/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 1/31/2024 Approved DAVID ANDERSON
HVAC-Rough 1/31/2024 Approved DAVID ANDERSON
PLUMBING-Rough 1/31/2024 Approved DAVID ANDERSON
Insulation 2/13/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/22/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Approved DAVID ANDERSON
Green Building Rough 2/22/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/22/2024 Approved DAVID ANDERSON
Drywall Nailing 2/27/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/11/2024 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 6/26/2024 Approved DAVID ANDERSON
Smoke Detectors 6/26/2024 Approved DAVID ANDERSON
Final 9/3/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 9/3/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved DAVID ANDERSON