3909 S MICHAEL AVE 90066
Certificate Information: 3909 S MICHAEL AVE 90066
- Application / Permit
- 23014-10000-04223
- Plan Check / Job No.
- B23LA19351
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- REMODEL, REMOVE TRELLIS, AND IRREGULAR SHAPED 23'-0" x 41'-8" ADDITION TO EXTEND KITCHEN, CREATE BEDROOM TO (E) DUPLEX PER ENGINEERING. NFPA-13D SPRINKLER SYSTEM THRU-OUT.
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2023 | ALFRED RAMIREZ |
| Corrections Issued | 10/19/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/4/2023 | OMAR GARNICA |
| Plan Check Approved | 1/10/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/16/2024 | APPLICANT |
| CofO in Progress | 10/10/2024 | JESUS PINEDA |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/20/2023 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 1/2/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/5/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/5/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2024 | DARIN LAM |
Contact Information
| Architect | Liu,, Siyuan; Lic. No.: NA39404 | , |
| Contractor | E H Construction Llc; Lic. No.: 1093006-B | , |
| Engineer | Zhang,, Jiefu; Lic. No.: NA5270 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/1/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/1/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/12/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/12/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/12/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/24/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 5/20/2024 | Approved | HERBERT GIRON |
| Insulation | 5/20/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/20/2024 | Approved | HERBERT GIRON |
| Shower Pan | 5/20/2024 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 5/28/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 5/28/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/29/2024 | Corrections Issued | JESUS PINEDA |
| Final | 8/29/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/29/2024 | Approved | JESUS PINEDA |
| Green Building Final | 8/29/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 8/29/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/29/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/29/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/10/2024 | Approved | JESUS PINEDA |
| Final | 10/10/2024 | OK to Issue CofO | JESUS PINEDA |
| PLUMBING-Final | 10/10/2024 | Approved | JESUS PINEDA |