144 N HARVARD BLVD 90004
Certificate Information: 144 N HARVARD BLVD 90004
- Application / Permit
- 23014-10000-04222
- Plan Check / Job No.
- B23LA17378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) GARAGE TO ADU WITH ADDITION AND ATATCHED STORAGE. DETCAHED ADU PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 10/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | ADRIANA LOPEZ |
| Corrections Issued | 10/12/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 11/7/2023 | FARUK SEZER |
| Applicant returned to address corrections | 5/21/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/12/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 12/6/2024 | ADRIANA LOPEZ |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 10/21/2025 | JEFFREY MEAD |
| Permit Finaled | 10/26/2025 | DEROLD HAUFF |
| CofO Issued | 10/26/2025 | DEROLD HAUFF |
| Permit Finaled | 10/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 6/3/2024 | LAMBERT GIESSINGER |
Contact Information
| Contractor | South Coast Construction & Development; Lic. No.: 1000004-B | , |
| Engineer | Velasco,, Jose Luis; Lic. No.: C76091 | 7901 4TH ST. N STE 5086 ST. PETERSBURG, FL 33702 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2025 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 2/18/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 2/18/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 4/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 4/8/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/11/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/11/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/11/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 4/11/2025 | Corrections Issued | JEFFREY MEAD |
| Insulation | 4/21/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 4/25/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | ALEX COLIN |
| Shower Pan | 4/25/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/13/2025 | Approved | JEFFREY MEAD |
| Final | 7/28/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/28/2025 | Approved | JEFFREY MEAD |
| Green Building Final | 7/28/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Not Required | JEFFREY MEAD |
| Smoke Detectors | 7/28/2025 | Approved | JEFFREY MEAD |
| Final | 9/4/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 9/9/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 10/20/2025 | OK to Issue CofO | JEFFREY MEAD |