144 N HARVARD BLVD 90004

Certificate Information: 144 N HARVARD BLVD 90004

Application / Permit
23014-10000-04222
Plan Check / Job No.
B23LA17378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) GARAGE TO ADU WITH ADDITION AND ATATCHED STORAGE. DETCAHED ADU PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
CofO Issued on 10/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 ADRIANA LOPEZ
Corrections Issued 10/12/2023 ADRIANA LOPEZ
Quality Review Completed 11/7/2023 FARUK SEZER
Applicant returned to address corrections 5/21/2024 ADRIANA LOPEZ
Applicant returned to address corrections 9/12/2024 ADRIANA LOPEZ
Plan Check Approved 12/6/2024 ADRIANA LOPEZ
Issued 1/17/2025 APPLICANT
CofO in Progress 10/21/2025 JEFFREY MEAD
Permit Finaled 10/26/2025 DEROLD HAUFF
CofO Issued 10/26/2025 DEROLD HAUFF
Permit Finaled 10/26/2025 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 6/3/2024 LAMBERT GIESSINGER

Contact Information

Contractor South Coast Construction & Development; Lic. No.: 1000004-B       ,
Engineer Velasco,, Jose Luis; Lic. No.: C76091 7901 4TH ST. N STE 5086      ST. PETERSBURG, FL 33702

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2025 Approved JEFFREY MEAD
Special/Order Compliance 2/18/2025 Approved JEFFREY MEAD
Underground Mechanical 2/18/2025 Approved JEFFREY MEAD
Footing/Foundation/Slab 2/24/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 4/8/2025 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval JEFFREY MEAD
PLUMBING-Rough 4/8/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 4/11/2025 Conditional Approval JEFFREY MEAD
ELECTRICAL-Rough 4/11/2025 Approved JEFFREY MEAD
Green Building Rough 4/11/2025 Approved JEFFREY MEAD
HVAC-Rough 4/11/2025 Corrections Issued JEFFREY MEAD
Insulation 4/21/2025 Approved RONNIE MINDANAO
Drywall Nailing 4/25/2025 Approved ALEX COLIN
Interior/Exterior Lathing 4/25/2025 Partial Approval ALEX COLIN
Shower Pan 4/25/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 6/13/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/13/2025 Approved JEFFREY MEAD
Final 7/28/2025 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 7/28/2025 Approved JEFFREY MEAD
Green Building Final 7/28/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Required JEFFREY MEAD
Smoke Detectors 7/28/2025 Approved JEFFREY MEAD
Final 9/4/2025 Corrections Issued JEFFREY MEAD
Final 9/9/2025 Corrections Issued JEFFREY MEAD
Final 10/20/2025 OK to Issue CofO JEFFREY MEAD