12859 W GILMORE AVE 90066
Certificate Information: 12859 W GILMORE AVE 90066
- Application / Permit
- 23014-10000-04207
- Plan Check / Job No.
- B23LA19256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 1ST AND 2ND FLOOR ADDITION TO (E) 2-CAR GARAGE TO HAVE ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g) ON TOP AND ATTACHED PATIO COVER ON 1ST FLOOR
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/29/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/8/2023 | TU HUA |
| Applicant returned to address corrections | 1/23/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 1/26/2024 | MAHNAZ NOURHASHEMI |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 12/5/2024 | MICHAEL ALLEN |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 11/1/2023 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 11/27/2023 | ALESSANDRO MERCURI |
| Low Impact Development (LID) | Cleared | 1/17/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Bela Remodeling; Lic. No.: 1038287-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/27/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 6/26/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 7/24/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 7/29/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 8/26/2024 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 8/27/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 9/3/2024 | Partial Approval | TEMISTOCLES CAAL |
| Gas Test | 9/17/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/17/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/2/2024 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 12/2/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 12/2/2024 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 12/2/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 12/4/2024 | Approved | MICHAEL ALLEN |
| Final | 12/4/2024 | OK to Issue CofO | MICHAEL ALLEN |
| Service/Power Release | 12/4/2024 | Approved | MICHAEL ALLEN |