13220 W LUCILLE AVE 90066
Certificate Information: 13220 W LUCILLE AVE 90066
- Application / Permit
- 23014-10000-04205
- Plan Check / Job No.
- B23LA19250
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 1ST AND 2ND FLOOR ADDITION TO (E) 2-CAR GARAGE TO HAVE ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/23/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/29/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/8/2023 | TU HUA |
| Plan Check Approved | 4/17/2024 | MAHNAZ NOURHASHEMI |
| No Progress | 4/17/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/19/2024 | MAHNAZ NOURHASHEMI |
| Issued | 7/23/2024 | APPLICANT |
| Refund in Progress | 8/14/2024 | SELENIA GARCIA |
| Refund in Progress | 8/14/2024 | SELENIA GARCIA |
| Refund Closed | 8/14/2024 | SELENIA GARCIA |
| Issued | 8/14/2024 | SELENIA GARCIA |
| Refund Closed | 8/14/2024 | SELENIA GARCIA |
| Issued | 8/14/2024 | SELENIA GARCIA |
| CofO in Progress | 8/5/2025 | WILBER ROSALES |
| Permit Finaled | 8/14/2025 | RICHARD STEINBACH |
| CofO Issued | 8/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/22/2024 | DARIN LAM |
| Specific Plan | Cleared | 5/15/2024 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 7/18/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: NA58024 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/18/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 10/23/2024 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 1/6/2025 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 1/30/2025 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 3/18/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 3/18/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Grounding or Bonding | 4/8/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 4/8/2025 | Corrections Issued | MICHAEL ALLEN |
| Shower Pan | 5/7/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 7/25/2025 | Approved | WILBER ROSALES |
| Final | 7/25/2025 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 7/25/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 7/25/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 7/25/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 7/25/2025 | Approved | WILBER ROSALES |
| Final | 7/31/2025 | OK to Issue CofO | WILBER ROSALES |
| Special/Order Compliance | 8/6/2025 | Corrections Issued | DAVID FEILER |