3944 W EDENHURST AVE 90039
Certificate Information: 3944 W EDENHURST AVE 90039
- Application / Permit
- 23014-10000-04192
- Plan Check / Job No.
- B23LA19181
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION OF 18'-11" X 20'-6" AT REART TO CREATE NEW FAMILY ROOM TO (E) SFD. ALL WORK PER ENG.
- Permit Issued
- Issued on 10/21/2023
- Issuing Office
- Current Status
- Issued on 10/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/17/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/20/2023 | LUISANGEL VALENZUELA |
| Issued | 10/21/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 10/18/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 10/18/2023 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/21/2023 | Conditional Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 11/27/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/6/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/6/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/3/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/3/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/10/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/10/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/24/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/29/2024 | Approved | CHARLES BOGHOSKHAN |
| Final | 2/27/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/27/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/27/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 3/6/2024 | Partial Inspection | HAMIK HARTOUNIAN |