2390 N EDGEWATER TER 90039
Certificate Information: 2390 N EDGEWATER TER 90039
- Application / Permit
- 23014-10000-04191
- Plan Check / Job No.
- B23LA19179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert (E) Garage to (N) ADU with addition to ADU to build a 448 sf ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2023 | AMY GUEVARRA |
| Corrections Issued | 10/19/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/3/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/17/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 11/20/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 12/1/2023 | ALFREDO JARA |
| Plan Check Approved | 12/8/2023 | ALFREDO JARA |
| Issued | 2/8/2024 | APPLICANT |
| CofO in Progress | 6/18/2024 | JOSEPH MCGARRY |
| Permit Finaled | 6/25/2024 | DEROLD HAUFF |
| CofO Issued | 6/25/2024 | DEROLD HAUFF |
| Permit Finaled | 6/25/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 10/25/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 10/25/2023 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 10/26/2023 | SERGIO VALENZUELA |
Contact Information
| Architect | Rodriguez,, Hector Manuel; Lic. No.: NA39395 | , |
| Contractor | Building Blocks Ca Llc; Lic. No.: 1034808-B | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: NA83347 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/20/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/20/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/27/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/9/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/9/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 4/9/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 4/9/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/11/2024 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 4/11/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/18/2024 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 4/18/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/18/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 4/18/2024 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 4/24/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/29/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/2/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/5/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/5/2024 | Corrections Issued | JOSEPH MCGARRY |
| Final | 6/5/2024 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/5/2024 | Approved | JOSEPH MCGARRY |
| Green Building Final | 6/5/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 6/5/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 6/5/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 6/5/2024 | Approved | JOSEPH MCGARRY |
| Final | 6/12/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 6/12/2024 | Approved | JOSEPH MCGARRY |