4211 S ALLA ROAD 90066
Certificate Information: 4211 S ALLA ROAD 90066
- Application / Permit
- 23014-10000-04169
- Plan Check / Job No.
- B23LA19095
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO EXISTING 1 STORY SINGLE FAMILY DWELLING AND NEW REAR COVERED DECK
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/21/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 10/24/2023 | APPLICANT |
| Applicant returned to address corrections | 4/17/2024 | HUAN LE |
| Plan Check Approved | 5/31/2024 | ADAM HEGAZI |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 6/4/2025 | MICHAEL ALLEN |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
| CofO Issued | 6/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 5/6/2024 | DARIN LAM |
| Specific Plan | Cleared | 6/18/2024 | FREDDY GARCIA |
Contact Information
| Architect | Sobhani,, Jamsheed Madadkar; Lic. No.: C29736 | 9045 BERTRAND AVENUE NORTHRIDGE, CA 913252811 |
| Contractor | New Hope Construction Inc; Lic. No.: 1063581-B | 7108 DE SOTO AVE SUITE 201 CANOGA PARK, CA 91303 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/16/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/19/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/29/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/29/2024 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 8/29/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 9/10/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/10/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/3/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 10/3/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 10/24/2024 | Approved | JESUS PINEDA |
| Insulation | 10/24/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 11/6/2024 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/15/2024 | Approved | REGINA MENDEZ |
| Shower Pan | 11/15/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 2/3/2025 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| Final | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 2/19/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/6/2025 | Approved | MICHAEL ALLEN |
| Final | 3/6/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 3/6/2025 | Partial Approval | MICHAEL ALLEN |
| HVAC-Final | 3/6/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/6/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 3/6/2025 | Partial Approval | RUBEN RIVAS |
| Service/Power Release | 3/7/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 3/11/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 6/3/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Green Building Final | 6/3/2025 | Approved | MICHAEL ALLEN |
| Order to Comply | 6/3/2025 | Not Required | MICHAEL ALLEN |