8408 N HANNA AVE 91304
Certificate Information: 8408 N HANNA AVE 91304
- Application / Permit
- 23014-10000-04154
- Plan Check / Job No.
- B23LA19030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 1-STORY SFD W/ATT GARAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2023 | MINA HABILI |
| Corrections Issued | 10/11/2023 | MINA HABILI |
| Applicant returned to address corrections | 1/16/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/24/2024 | SERGIO MUNIZ |
| Issued | 5/9/2024 | APPLICANT |
| CofO in Progress | 7/3/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/9/2024 | JOHN JANSON |
| CofO Issued | 7/9/2024 | JOHN JANSON |
| Permit Finaled | 7/9/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/30/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/30/2023 | CARLOS RAMIREZ |
| Tenant Habitability Plan | Cleared | 12/6/2023 | RICARDO BOHORQUEZ |
| Grading Pre-Inspection | Cleared | 1/23/2024 | CHARLES POWELL |
Contact Information
| Contractor | L A T Construction Inc; Lic. No.: 1038128-B | 13275 BRANFORD STREET ARLETA, CA 91321 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2024 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/10/2024 | Approved | CHRIS CHRISTENSEN |
| Sewer | 5/10/2024 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/10/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/21/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/21/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/21/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/21/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/21/2024 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 5/21/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/28/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/30/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/4/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 6/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/27/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 7/2/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |