4031 S BEETHOVEN ST 90066

Certificate Information: 4031 S BEETHOVEN ST 90066

Application / Permit
23014-10000-04128
Plan Check / Job No.
B23LA18912
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - MAJOR REMODEL AND 2ND STORY ADDITION TO EXISTING SFD
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 2/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 STARR CHEN
Plan Check Approved 4/3/2024 STARR CHEN
No Progress 4/3/2024 STARR CHEN
Plan Check Approved 4/3/2024 STARR CHEN
Issued 4/3/2024 APPLICANT
CofO in Progress 2/20/2025 JESUS PINEDA
CofO Issued 2/21/2025 RICHARD STEINBACH
Permit Finaled 2/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/25/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/26/2023 DARIN LAM
Sewer availability Cleared 10/26/2023 DARIN LAM
Specific Plan Cleared 11/7/2023 FREDDY GARCIA

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: NA22676       ,
Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Kennedy,, Nicholas; Lic. No.: S6884 3664 FENWAY STREET      FOREST GROVE, OR 97116

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/9/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/9/2024 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 4/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/13/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/13/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/26/2024 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 6/26/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Corrections Issued KIRK SANDERS
Green Building Rough 6/26/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 6/26/2024 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 6/26/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 6/28/2024 Corrections Issued KIRK SANDERS
Green Building Rough 6/28/2024 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 6/28/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 7/1/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 7/1/2024 Partial Approval JESUS RODRIGUEZ
Deputy Wood Construction 7/5/2024 Conditional Approval MICHAEL PELHAM
HVAC-Rough 7/9/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 7/12/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/12/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 7/26/2024 Approved REGINA MENDEZ
Special/Order Compliance 7/26/2024 Approved JESUS RODRIGUEZ
Insulation 7/30/2024 Not Ready for Inspection SEAN HAUPT
Insulation 8/1/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved JESUS RODRIGUEZ
Deputy Wood Construction 8/7/2024 Conditional Approval TEMISTOCLES CAAL
Drywall Nailing 8/14/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 9/6/2024 Partial Inspection JESUS PINEDA
Special/Order Compliance 9/27/2024 Partial Inspection JESUS PINEDA
Special/Order Compliance 10/7/2024 Approved JESUS PINEDA
Drywall Nailing 10/9/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 12/2/2024 Not Ready for Inspection JESUS PINEDA
Final 12/2/2024 Corrections Issued JESUS PINEDA
Green Building Final 12/2/2024 Not Ready for Inspection JESUS PINEDA
Green Building Rough 12/2/2024 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready JESUS PINEDA
Service/Power Release 12/2/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 12/2/2024 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 12/2/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 12/3/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 12/31/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Final 12/31/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 12/31/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 1/6/2025 Corrections Issued JESUS PINEDA
HVAC-Final 1/6/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 1/6/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 1/13/2025 Approved JESUS PINEDA
PLUMBING-Final 1/13/2025 Approved JESUS PINEDA
Pre-Inspection 2/7/2025 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 2/11/2025 Approved JESUS PINEDA
Final 2/11/2025 Corrections Issued JESUS PINEDA
Green Building Final 2/11/2025 Approved JESUS PINEDA
Green Building Rough 2/11/2025 Approved JESUS PINEDA
HVAC-Final 2/11/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 2/11/2025 Approved JESUS PINEDA
Verify Sprinkler Sign Off 2/11/2025 Approved JESUS PINEDA
Final 2/19/2025 OK to Issue CofO JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 2/19/2025 Approved JESUS PINEDA