2013 1/2 W 84TH ST 90047
Certificate Information: 2013 1/2 W 84TH ST 90047
- Application / Permit
- 23014-10000-04127
- Plan Check / Job No.
- B23LA18909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: ADD TO AND CONVERT EXISTING DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) COMPLY WITH DEPARTMENT ORDER effective date 04/12/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | JASON JANGADA |
| Corrections Issued | 10/14/2023 | JASON JANGADA |
| Applicant returned to address corrections | 5/29/2024 | AMY GUEVARRA |
| Plan Check Approved | 6/5/2024 | AMY GUEVARRA |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | JAVIER RAMOS SR |
| No Progress | 4/9/2026 | JAVIER RAMOS SR |
| CofO in Progress | 4/9/2026 | JAVIER RAMOS SR |
| CofO in Progress | 4/13/2026 | JAVIER RAMOS SR |
| CofO in Progress | 4/13/2026 | JAVIER RAMOS SR |
| CofO in Progress | 4/13/2026 | JAVIER RAMOS SR |
| No Progress | 4/13/2026 | JAVIER RAMOS SR |
| CofO in Progress | 4/13/2026 | JAVIER RAMOS SR |
| Permit Finaled | 4/30/2026 | CLAUDIO MORENO |
| CofO Issued | 4/30/2026 | CLAUDIO MORENO |
| Permit Finaled | 4/30/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2023 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/27/2023 | JUSTIN BICOL |
| Construction near power lines | Cleared | 2/10/2024 | RIDWAN HARDY |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: C36271 | 26030 SANDBURG PL STEVENSON RANCH, CA 91381 |
| Architect | Hanna,, Remon; Lic. No.: NA36271 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/7/2024 | Approved | MICHAEL SERETTI |
| Pre-Inspection | 8/7/2024 | Approved | MICHAEL SERETTI |
| Deputy Drilled-In Anchors | 8/14/2024 | Approved | MICHAEL SERETTI |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | MICHAEL SERETTI |
| Pre-Inspection | 8/14/2024 | Approved | MICHAEL SERETTI |
| Footing/Foundation/Slab | 9/10/2024 | Partial Approval | MICHAEL SERETTI |
| Footing/Foundation/Slab | 9/13/2024 | Partial Approval | MICHAEL SERETTI |
| PLUMBING-Rough | 9/26/2024 | Partial Approval | MICHAEL SERETTI |
| Sewer | 9/26/2024 | Approved | MICHAEL SERETTI |
| Footing/Foundation/Slab | 10/1/2024 | Approved | MICHAEL SERETTI |
| BUILDING-Rough-Frame | 10/22/2024 | Partial Approval | MICHAEL SERETTI |
| Green Building Rough | 10/22/2024 | Approved | MICHAEL SERETTI |
| Interior/Exterior Lathing | 11/1/2024 | Partial Approval | MICHAEL SERETTI |
| ELECTRICAL-Rough | 11/7/2024 | Partial Approval | MICHAEL SERETTI |
| ELECTRICAL-Rough | 11/13/2024 | Approved | MICHAEL SERETTI |
| PLUMBING-Rough | 11/13/2024 | Approved | MICHAEL SERETTI |
| Insulation | 11/15/2024 | Approved | MICHAEL SERETTI |
| Drywall Nailing | 12/6/2024 | Approved | MICHAEL SERETTI |
| Interior/Exterior Lathing | 12/6/2024 | Approved | MICHAEL SERETTI |
| BUILDING-Rough-Frame | 1/31/2025 | Approved | MICHAEL SERETTI |
| Final | 1/31/2025 | Corrections Issued | MICHAEL SERETTI |
| Green Building Final | 1/31/2025 | Approved | MICHAEL SERETTI |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Not Ready | MICHAEL SERETTI |
| Smoke Detectors | 1/31/2025 | Not Ready for Inspection | MICHAEL SERETTI |
| Final | 2/6/2025 | OK to Issue CofO | MICHAEL SERETTI |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | MICHAEL SERETTI |
| Smoke Detectors | 2/6/2025 | Approved | MICHAEL SERETTI |