141 W 28TH ST 90007

Certificate Information: 141 W 28TH ST 90007

Application / Permit
23014-10000-04087
Plan Check / Job No.
B23LA18761
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM FACTORY TO OFFICE AND INTERIOR/ EXTERIOR ALTERATION ON (E) ONE STORY, TYPE III-B, 54FT X 92 FT, SPRINKLERED BUILDING. 1 OF 2
Permit Issued
Issued on 3/26/2025
Issuing Office
Metro
Current Status
Issued on 3/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 TSE MING HUANG
Corrections Issued 10/24/2023 TSE MING HUANG
Quality Review Completed 10/25/2023 KEN GILL
Building Plans Picked Up 10/30/2023 APPLICANT
Applicant returned to address corrections 12/14/2023 TSE MING HUANG
Disabled Access Plans Picked Up 1/16/2024 APPLICANT
Applicant returned to address corrections 1/23/2024 TSE MING HUANG
Applicant returned to address corrections 2/14/2024 TSE MING HUANG
Applicant returned to address corrections 4/18/2024 TSE MING HUANG
Plan Check Approved 5/3/2024 TSE MING HUANG
Issued 3/26/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/23/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 1/25/2024 JUSTIN BICOL
Green Code Cleared 1/30/2024 AARON COSTA
Redevelopment Project Area Cleared 4/22/2024 YASMINE BASHIRI
ZI Cleared 4/22/2024 YASMINE BASHIRI
DAS Clearance Cleared 5/2/2024 TSE MING HUANG

Contact Information

Architect Koning,, Hendrik; Lic. No.: C13530 1454 25TH STREET      SANTA MONICA, CA 90404
Contractor S 3 Builders Inc; Lic. No.: 928330-B P O BOX 11478      BURBANK, CA 91510
Engineer John,, Benjamin Morgan; Lic. No.: S6932 1541 SE MAPLE AVE      PORTLAND, OR 97214

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/8/2026   
Smoke Detectors 6/8/2026   
SGSOV-Seismic Gas S/O Valve 6/8/2026   

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 7/31/2025 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 8/22/2025 Partial Approval ALFREDO LOPEZ
Insulation 9/24/2025 Partial Approval ALFREDO LOPEZ
Wood Frame 9/24/2025 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 10/9/2025 Partial Approval ALFREDO LOPEZ
Wood Frame 10/9/2025 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 11/13/2025 Partial Approval ALFREDO LOPEZ
Special/Order Compliance 11/13/2025 Partial Inspection REGINA MENDEZ
Wood Frame 11/13/2025 Approved ALFREDO LOPEZ
Pre-Inspection 3/16/2026 Partial Approval PAUL BAZERKANIAN
Final 5/29/2026 Partial Inspection ALFREDO LOPEZ
Green Building Final 5/29/2026 Approved ALFREDO LOPEZ
Green Building Rough 5/29/2026 Approved ALFREDO LOPEZ
METHANE-Final 5/29/2026 Approved ALFREDO LOPEZ
METHANE-Rough 5/29/2026 Approved ALFREDO LOPEZ
Reinforced Masonry Frame 5/29/2026 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 5/29/2026 Not Ready for Inspection ALFREDO LOPEZ