462 N FLORES ST 90048
Certificate Information: 462 N FLORES ST 90048
- Application / Permit
- 23014-10000-04064
- Plan Check / Job No.
- B23LA18631
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SFD TO ATTACHED DETACHED GARAGE AND CONVERT TO BEDROOM AND BATHROOM WITH STUDY. NEW ATTACHED CARPORT. REMODEL EX. SFD PER PLANS.
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Current Status
- Issued on 11/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/7/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/21/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/28/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 4/2/2024 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/6/2024 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/10/2024 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/20/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/26/2024 | ALEC MOUSAKHANIAN |
| Issued | 11/15/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/18/2023 | DAVID LOPEZ |
| Construction near power lines | Cleared | 2/21/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 3/15/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/18/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Sarahang Construction Inc; Lic. No.: 897724-B | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 12/26/2024 | Partial Approval | JOSE MACIAS |
| METHANE-Barrier | 12/26/2024 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 12/26/2024 | Approved | JOSE MACIAS |
| Pre-Inspection | 5/2/2025 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 10/21/2025 | Corrections Issued | JOSH MEISTER |
| Pre-Inspection | 5/29/2026 | Corrections Issued | JOSH MEISTER |