9291-9293 N STANWIN AVE 91331
Certificate Information: 9291-9293 N STANWIN AVE 91331
- Application / Permit
- 23014-10000-04062
- Plan Check / Job No.
- B23LA18623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Partial Conversion with Addition of (E) SFD to SFD with an attached (607 sf) Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (e). Remodel at bathroom.
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2023 | MICHAEL LANZONE |
| Corrections Issued | 10/11/2023 | MICHAEL LANZONE |
| Building Plans Picked Up | 10/17/2023 | APPLICANT |
| Plan Check Approved | 11/9/2023 | SHANGQIN XIE |
| Issued | 11/20/2023 | APPLICANT |
| CofO in Progress | 9/9/2024 | MICHEL ABAJAN |
| CofO Issued | 9/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2023 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 11/2/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/8/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2024 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 3/22/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/5/2024 | Corrections Issued | MICHEL ABAJAN |
| Sewer | 4/5/2024 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/8/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/15/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/10/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/10/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/10/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/10/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/20/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/20/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 6/20/2024 | Partial Inspection | MICHEL ABAJAN |
| Drywall Nailing | 7/3/2024 | Not Ready for Inspection | LEONARD ROSS II |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Not Ready for Inspection | LEONARD ROSS II |
| Insulation | 7/3/2024 | Approved | LEONARD ROSS II |
| Interior/Exterior Lathing | 7/3/2024 | Approved | LEONARD ROSS II |
| Shower Pan | 7/3/2024 | Partial Approval | LEONARD ROSS II |
| Drywall Nailing | 7/8/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/8/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/25/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/6/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/6/2024 | Approved | MICHEL ABAJAN |
| Final | 9/6/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/6/2024 | Approved | MICHEL ABAJAN |
| Green Building Final | 9/6/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 9/6/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/6/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 9/6/2024 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/6/2024 | Approved | MICHEL ABAJAN |