3362 S ROSEWOOD AVE 90066
Certificate Information: 3362 S ROSEWOOD AVE 90066
- Application / Permit
- 23014-10000-04052
- Plan Check / Job No.
- B23LA18596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION TO (E) ONE STORY SFD W/ ATTACHED TWO CAR GARAGE. FIRE SPRINKLERS NFPA 13D REQUIRED THROGHOUT. "COMPLY WITH DEPARTMENT ORDER effective date 02/14/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Current Status
- Permit Expired on 12/15/2025
- Certificate of Occupancy
- Permit Expired More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 10/10/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/11/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/16/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/13/2024 | SERGIO GUTIERREZ |
| Issued | 2/13/2024 | APPLICANT |
| Permit Closed | 12/12/2025 | ANDREW BEELI |
| CofO in Progress | 12/12/2025 | ANDREW BEELI |
| Permit Expired | 12/15/2025 | CLAUDIO MORENO |
| CofO in Progress | 12/15/2025 | RYAN BARNES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/10/2023 | SERGIO GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/28/2023 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/31/2023 | DARIN LAM |
| Specific Plan | Cleared | 11/6/2023 | MOHAMMAD HASAN |
| Low Impact Development (LID) | Cleared | 12/8/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 12/17/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/6/2024 | Approved | RYAN BARNES |
| HVAC-Rough | 3/27/2024 | Corrections Issued | JOHN MATTILLO |
| PLUMBING-Rough | 3/27/2024 | Partial Approval | JOHN MATTILLO |
| BUILDING-Rough-Frame | 3/28/2024 | Partial Approval | JOHN MATTILLO |
| Green Building Rough | 3/28/2024 | Not Ready for Inspection | JOHN MATTILLO |
| HVAC-Rough | 3/28/2024 | Partial Approval | JOHN MATTILLO |
| ELECTRICAL-Rough | 5/21/2025 | Approved | RYAN BARNES |
| HVAC-Rough | 5/21/2025 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | RYAN BARNES |
| Green Building Rough | 5/22/2025 | Approved | RYAN BARNES |
| Shower Pan | 6/6/2025 | Partial Approval | ANDREW BEELI |
| Insulation | 6/11/2025 | Approved | RYAN BARNES |
| Shower Pan | 6/11/2025 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 6/17/2025 | Approved | RYAN BARNES |
| Drywall Nailing | 6/25/2025 | Approved | RYAN BARNES |
| PLUMBING-Final | 10/21/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 11/13/2025 | Approved | RYAN BARNES |
| Final | 11/13/2025 | Conditional Approval | RYAN BARNES |
| Footing/Foundation/Slab | 11/13/2025 | Approved | RYAN BARNES |
| Green Building Final | 11/13/2025 | Approved | RYAN BARNES |
| HVAC-Final | 11/13/2025 | Approved | RYAN BARNES |
| PLUMBING-Final | 11/13/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 11/13/2025 | Approved | RYAN BARNES |
| Final | 12/12/2025 | Permit Closed | ANDREW BEELI |