4226 N COLLIS AVE 90032

Certificate Information: 4226 N COLLIS AVE 90032

Application / Permit
23014-10000-04051
Plan Check / Job No.
B23LA18595
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: PROPOSED 1-STORY VAULTED ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING TO CREATE ONE BEDROOM AND ONE BATHROOM.
Permit Issued
Issued on 2/26/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/3/2024 MICHAEL LOPEZ
Corrections Issued 1/4/2024 MICHAEL LOPEZ
Applicant returned to address corrections 2/21/2024 MICHAEL LOPEZ
Plan Check Approved 2/26/2024 MICHAEL LOPEZ
Issued 2/26/2024 APPLICANT
CofO in Progress 5/9/2025 LILIANA PORTILLO
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/3/2024 ROBERT HUGHES
Roof/Waste drainage to street Cleared 1/11/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/18/2024 WALLIE JONG
Sewer availability Cleared 1/18/2024 WALLIE JONG
"D" conditions Cleared 2/15/2024 MAYELA VILLA
"Q" conditions Cleared 2/15/2024 MAYELA VILLA
ZI Cleared 2/15/2024 MAYELA VILLA

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2024 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 4/4/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 4/4/2024 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 4/30/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/30/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval LILIANA PORTILLO
HVAC-Rough 4/30/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 4/30/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/13/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 5/13/2024 Approved LILIANA PORTILLO
Green Building Rough 5/13/2024 Not Ready for Inspection LILIANA PORTILLO
Insulation 5/13/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 5/13/2024 Approved LILIANA PORTILLO
Drywall Nailing 5/28/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/28/2024 Partial Approval LILIANA PORTILLO
Shower Pan 5/28/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/12/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/14/2024 Approved LILIANA PORTILLO
Final 11/14/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 11/14/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 11/14/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/14/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/22/2024 Approved LILIANA PORTILLO
Final 11/22/2024 Conditional Approval LILIANA PORTILLO
Green Building Final 11/22/2024 Approved LILIANA PORTILLO
HVAC-Final 11/22/2024 Approved LILIANA PORTILLO
PLUMBING-Final 11/22/2024 Approved LILIANA PORTILLO
Final 5/8/2025 OK to Issue CofO LILIANA PORTILLO