1244 W 27TH ST 90731

Certificate Information: 1244 W 27TH ST 90731

Application / Permit
23014-10000-04006
Plan Check / Job No.
B23LA18377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: addition and remodel to existing dwelling per ADM-2023-6625-CEX. improvement include porch, kitchen, living room, dining room, bed room, bathroom
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
Issued on 4/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 KHUONG TRUONG
Corrections Issued 11/2/2023 KHUONG TRUONG
Applicant returned to address corrections 4/2/2024 KHUONG TRUONG
Applicant returned to address corrections 5/23/2024 AUNG SOE
Applicant returned to address corrections 5/29/2024 RICARDO RAMIREZ
Applicant returned to address corrections 7/10/2024 AUNG SOE
Plan Check Approved 7/10/2024 AUNG SOE
No Progress 7/10/2024 AUNG SOE
Plan Check Approved 4/25/2025 AUNG SOE
Issued 4/28/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/16/2024 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 5/22/2024 KHAING AYE
Roof/Waste drainage to street Cleared 5/22/2024 KHAING AYE
Sewer availability Cleared 5/22/2024 KHAING AYE
Grading Pre-Inspection Cleared 5/29/2024 KHUONG TRUONG
GPI Written Notices Cleared 7/9/2024 RICARDO RAMIREZ
Coastal Zone Cleared 2/28/2025 FIPE LEILUA

Contact Information

Contractor Owner-Builder       ,
Engineer Chaiprasert,, Victor V; Lic. No.: C36235 17703 CRENSHAW BLVD      TORRANCE, CA 90504

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2025 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 5/29/2025 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 6/4/2025 Partial Inspection JOHN KLARIN
Insulation 6/4/2025 Partial Inspection JOHN KLARIN
Wood Frame 6/9/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 6/17/2025 Partial Approval JOSEPH MCGARRY
Service/Power Release 6/17/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 7/1/2025 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 7/3/2025 Conditional Approval JOSEPH MCGARRY
Green Building Rough 7/3/2025 Approved JOSEPH MCGARRY
HVAC-Rough 7/3/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/3/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/10/2025 Approved JOSEPH MCGARRY
Insulation 7/10/2025 Approved JOSEPH MCGARRY
Drywall Nailing 7/17/2025 Approved ANTHONY EGSON
Shower Pan 8/21/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/26/2025 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 12/3/2025 Approved JOSEPH MCGARRY