ePlan. Convert existing 2-CAR garage (442sqft) with new entry porch (12sqft) and W/D area (13sqft) into a new Accessory Dwelling Unit (467sqft) PER STATE LAW work done per wfpp
Permit Issued
Issued on 3/5/2024
Issuing Office
Current Status
CofO Issued on 6/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2023 APPLICANT
Assigned to Plan Check Engineer 10/24/2023 KHUONG TRUONG
Corrections Issued 10/24/2023 KHUONG TRUONG
Plan Check Approved 1/23/2024 KHUONG TRUONG
Issued 3/5/2024 APPLICANT
CofO in Progress 5/29/2025 EUGENE CASSIDY
Permit Finaled 6/2/2025 ANSON MAGLASANG
CofO Issued 6/2/2025 ANSON MAGLASANG
Permit Finaled 6/2/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/27/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 1/16/2024 KHAING AYE
Roof/Waste drainage to street Cleared 1/16/2024 KHAING AYE
Sewer availability Cleared 1/16/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/9/2024 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 8/13/2024 Approved EUGENE CASSIDY
METHANE-Barrier 8/13/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 8/13/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 8/13/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/23/2024 Approved EUGENE CASSIDY
Gas Test 9/23/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 9/23/2024 Approved EUGENE CASSIDY
Insulation 9/27/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 10/3/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Approved BEN MOLSTAD
Green Building Rough 10/3/2024 Approved BEN MOLSTAD
Insulation 10/3/2024 Approved BEN MOLSTAD
MERV13>=Rough 10/3/2024 Approved BEN MOLSTAD
METHANE-Rough 10/3/2024 Approved BEN MOLSTAD
Wood Frame 10/3/2024 Approved BEN MOLSTAD
Shower Pan 10/18/2024 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 10/23/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/23/2024 Partial Approval EUGENE CASSIDY
Shower Pan 10/23/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/5/2025 Approved EUGENE CASSIDY
Final 5/5/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 5/5/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 5/5/2025 Approved EUGENE CASSIDY
Smoke Detectors 5/5/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/29/2025 Approved EUGENE CASSIDY
Final 5/29/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 5/29/2025 Approved EUGENE CASSIDY
PLUMBING-Final 5/29/2025 Approved EUGENE CASSIDY
Smoke Detectors 5/29/2025 Approved EUGENE CASSIDY