1937 S BUCKINGHAM ROAD 90016

Certificate Information: 1937 S BUCKINGHAM ROAD 90016

Application / Permit
23014-10000-03994
Plan Check / Job No.
B23LA18325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
Issued on 2/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/30/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 CARLOS MONTES
Corrections Issued 10/17/2023 CARLOS MONTES
Quality Review Completed 10/17/2023 GARO TELMI
Applicant returned to address corrections 10/10/2024 CARLOS MONTES
Applicant returned to address corrections 10/30/2024 CARLOS MONTES
Applicant returned to address corrections 11/14/2024 CARLOS MONTES
Applicant returned to address corrections 1/10/2025 CARLOS MONTES
Plan Check Approved 1/30/2025 CARLOS MONTES
Issued 2/5/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/1/2024 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 9/27/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/27/2024 CHRISTINA BRACO
Sewer availability Cleared 9/27/2024 CHRISTINA BRACO

Contact Information

Contractor La Bay Homes; Lic. No.: 997020-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2025 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 3/7/2025 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 4/30/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/2/2025 Partial Approval ENRIQUE MIRELES
Green Building Rough 5/2/2025 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 5/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 5/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/22/2025 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued JUSTIN HAWLEY
Green Building Rough 6/10/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 6/10/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 6/30/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 6/30/2025 Approved JUSTIN HAWLEY
Insulation 7/8/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 7/8/2025 Approved JOSH MEISTER
Drywall Nailing 8/18/2025 Corrections Issued WILLIAM SIERRA
Drywall Nailing 8/20/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/17/2025 Approved ALEX COLIN
Shower Pan 9/17/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 3/17/2026 Approved JUSTIN HAWLEY
Final 3/17/2026 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 3/17/2026 Approved JUSTIN HAWLEY
Green Building Final 3/17/2026 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 3/17/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 3/17/2026 Approved JUSTIN HAWLEY