1430 W 69TH ST 90047

Certificate Information: 1430 W 69TH ST 90047

Application / Permit
23014-10000-03990
Plan Check / Job No.
B23LA18318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE TO BE CONVERTED INTO ADU = 361.87 SQFT. ADDITION = 155.80 SQFT. TOTAL ADU AREA = 517.67 SQFT. PER STATE LAW
Permit Issued
Issued on 6/21/2024
Issuing Office
Metro
Current Status
Issued on 6/21/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2023 APPLICANT
Assigned to Plan Check Engineer 10/2/2023 KHUONG TRUONG
Corrections Issued 10/4/2023 KHUONG TRUONG
Building Plans Picked Up 10/16/2023 APPLICANT
Plan Check Approved 5/22/2024 JOHN MESIAS
Issued 6/21/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/23/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 10/23/2023 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 10/23/2023 ARNULFO CHAMU
Sewer availability Cleared 10/23/2023 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/2/2024 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 10/9/2024 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Rough 10/10/2024 Partial Approval CRAIG DAVIS
Deputy Drilled-In Anchors 10/11/2024 Conditional Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 10/16/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 10/16/2024 Approved CRAIG DAVIS
Green Building Rough 10/16/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 10/17/2024 No Access for Inspection RUBEN SALAS
Reinforced Concrete Frame 10/17/2024 No Access for Inspection RUBEN SALAS
BUILDING-Rough-Frame 11/5/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 11/5/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval CRAIG DAVIS
Green Building Rough 11/5/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 12/6/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 12/6/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 12/6/2024 Approved JOSE MACIAS
Drywall Nailing 12/18/2024 Corrections Issued BARRY HACHE
HVAC-Rough 12/23/2024 Approved JOSE MACIAS
Insulation 12/23/2024 Approved JOSE MACIAS
Drywall Nailing 12/26/2024 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 1/6/2025 Approved BARRY HACHE
Drywall Nailing 1/6/2025 Approved BARRY HACHE
Green Building Rough 1/6/2025 Approved BARRY HACHE
Drywall Nailing 1/7/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 1/28/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 2/4/2025 Approved ANTHONY RAMOS
Shower Pan 2/4/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 2/25/2025 Approved BARRY HACHE
Wood Frame 3/20/2025 Approved BARRY HACHE
Final 8/14/2025 Corrections Issued BARRY HACHE
HVAC-Final 8/14/2025 Not Ready for Inspection BARRY HACHE