13944 W VALLEYHEART DR 91423
Certificate Information: 13944 W VALLEYHEART DR 91423
- Application / Permit
- 23014-10000-03976
- Plan Check / Job No.
- B23LA18254
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 1st AND 2nd FLOOR ADDITION TO AN (E) 1-STORY SFD WITH NEW ATT. GARAGE WITH MAJOR STR. REMODEL -ENTIRE BLDG IS EQUIPPED WITH SPRINKLER NFPA 13D
- Permit Issued
- Issued on 3/27/2024
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/20/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/27/2023 | TU HUA |
| Plan Check Approved | 2/28/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/20/2024 | RODOLFO ARIAS |
| Plan Check Approved | 3/26/2024 | RODOLFO ARIAS |
| Issued | 3/27/2024 | APPLICANT |
| CofO in Progress | 2/18/2025 | MISAEL ESPARZA |
| CofO in Progress | 3/8/2025 | MISAEL ESPARZA |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
| CofO Issued | 3/13/2025 | RUBEN SALAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 10/23/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 11/21/2023 | BRYAN GODINEZ |
| ZI | Cleared | 11/21/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | BRYAN GODINEZ |
| Hydrant and Access approval | Cleared | 12/9/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 1/30/2024 | PATRICK LOPEZ |
| Trees in Parkway | Cleared | 1/30/2024 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 2/1/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/22/2024 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 4/24/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/8/2024 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 5/10/2024 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 5/14/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/24/2024 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Rough | 5/24/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | MISAEL ESPARZA |
| MERV13>=Rough | 5/29/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/3/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 7/3/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/3/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/17/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/31/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/2/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/7/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Approved | MISAEL ESPARZA |
| Insulation | 8/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 8/21/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Shower Pan | 8/23/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/28/2024 | Conditional Approval | MISAEL ESPARZA |
| MERV13>=Rough | 8/28/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 8/28/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/5/2024 | Approved | MISAEL ESPARZA |
| Insulation | 9/5/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/12/2024 | Approved | MISAEL ESPARZA |
| Gas Test | 12/2/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 12/20/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 12/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 12/30/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 12/30/2024 | Conditional Approval | MISAEL ESPARZA |
| Gas Test | 1/2/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/13/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 1/13/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/24/2025 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/24/2025 | Corrections Issued | RAUL OLAGI |
| Final | 1/24/2025 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/24/2025 | Approved | RAUL OLAGI |
| HVAC-Final | 1/24/2025 | Approved | RAUL OLAGI |
| MERV13>=Final | 1/24/2025 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/24/2025 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/24/2025 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/13/2025 | Approved | MISAEL ESPARZA |
| Final | 2/13/2025 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 2/13/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 2/13/2025 | Approved | MISAEL ESPARZA |
| Service/Power Release | 2/13/2025 | Approved | MISAEL ESPARZA |
| Final | 3/7/2025 | OK to Issue CofO | MISAEL ESPARZA |