3670 S CORINTH AVE 90066

Certificate Information: 3670 S CORINTH AVE 90066

Application / Permit
23014-10000-03973
Plan Check / Job No.
B23LA18239
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION TO (E) SFD
Permit Issued
Issued on 11/16/2023
Issuing Office
Current Status
Issued on 11/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/28/2023 APPLICANT
Assigned to Plan Check Engineer 10/2/2023 JOSEPH RAFOLS
Corrections Issued 10/3/2023 JOSEPH RAFOLS
Plan Check Approved 11/8/2023 JOSEPH RAFOLS
Issued 11/16/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/10/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 10/23/2023 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 10/23/2023 LIAM ODONOVAN
Specific Plan Cleared 11/3/2023 JOSHUA JONES

Contact Information

Architect Guga,, Jeff; Lic. No.: C36577 3448 ASHWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Baad,, Katherine Firestone; Lic. No.: NA64669       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/30/2024 Corrections Issued JESUS PINEDA
Deputy Drilled-In Anchors 2/1/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 3/15/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 3/15/2024 Approved JESUS PINEDA
MERV13>=Rough 3/15/2024 Approved JESUS PINEDA
PLUMBING-Rough 3/15/2024 Approved JESUS PINEDA
Deputy Wood Construction 3/18/2024 Conditional Approval JESUS PINEDA
Insulation 4/4/2024 Corrections Issued TEMISTOCLES CAAL
Interior/Exterior Lathing 4/4/2024 Partial Approval TEMISTOCLES CAAL
Shower Pan 4/4/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/9/2024 Approved JESUS PINEDA
Green Building Rough 4/9/2024 Approved JESUS PINEDA
Insulation 4/9/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/9/2024 Approved JESUS PINEDA
Drywall Nailing 4/15/2024 Approved JESUS PINEDA
Final 7/24/2024 Corrections Issued JESUS PINEDA
Green Building Final 7/24/2024 Corrections Issued JESUS PINEDA
MERV13>=Final 7/24/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 7/24/2024 Corrections Issued JESUS PINEDA
Final 9/5/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 9/5/2024 Approved DANIEL VERA
Smoke Detectors 9/5/2024 Approved DANIEL VERA