1084 E NOWITA PL 90291

Certificate Information: 1084 E NOWITA PL 90291

Application / Permit
23014-10000-03972
Plan Check / Job No.
B23LA18230
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 29'-6" x 22'-5" IRREG. SHAPED ADDITION TO (E) SFD AND FIRE DAMAGE REPAIR OF (E) SFD. WORK DONE PER ENGINEER DESIGN.**NFPA-13D FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT**
Permit Issued
Issued on 8/13/2024
Issuing Office
Current Status
Permit Finaled on 8/13/2025

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/6/2023 MIROOSH KHACHATOORIAN
Corrections Issued 10/6/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 4/23/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/2/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/30/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 8/5/2024 SARKIS HARABEDIAN
Issued 8/13/2024 APPLICANT
Permit Finaled 8/13/2025 DAVID FEILER

Permit Application Clearance Information

Specific Plan Cleared 4/25/2024 MOHAMMAD HASAN
Roof/Waste drainage to street Cleared 5/4/2024 BRENDEN HAWK
Sewer availability Cleared 5/4/2024 BRENDEN HAWK
Low Impact Development (LID) Cleared 6/26/2024 JASMIN ASHLEY
Eng Process Fee Ord 176,300 Cleared 6/27/2024 BRENDEN HAWK

Contact Information

Contractor H P Associates Inc; Lic. No.: 740238-B       ,
Engineer Rivera,, Mark Paul; Lic. No.: C66864 6700 MARK TWAIN DR      PINETOP, AZ 85935

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/23/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 5/23/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/23/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 5/23/2025 Corrections Issued JESUS RODRIGUEZ
Insulation 6/5/2025 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 6/5/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/24/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 7/24/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 7/24/2025 Corrections Issued TEMISTOCLES CAAL
Final 7/24/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 7/24/2025 Approved TEMISTOCLES CAAL
Green Building Final 7/24/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Rough 7/24/2025 Approved TEMISTOCLES CAAL
HVAC-Final 7/24/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 7/24/2025 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Not Ready TEMISTOCLES CAAL
Smoke Detectors 7/24/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 7/30/2025 Approved JESUS RODRIGUEZ
Final 7/30/2025 Partial Approval JESUS RODRIGUEZ
Green Building Final 7/30/2025 Approved JESUS RODRIGUEZ
HVAC-Final 7/30/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 7/30/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved JESUS RODRIGUEZ
Final 8/13/2025 Permit Finaled DAVID FEILER