1093 S LE CLAIRE PL 90019
Certificate Information: 1093 S LE CLAIRE PL 90019
- Application / Permit
- 23014-10000-03971
- Plan Check / Job No.
- B23LA18229
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 240 SF DET GARAGE AND 18'-8" X 18'-1" ADDITION INTO A (N) 449.3 SF ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/3/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/3/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/4/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/7/2024 | LUISANGEL VALENZUELA |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | JUSTIN HAWLEY |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
| CofO Issued | 6/10/2025 | DEROLD HAUFF |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/29/2024 | RIDWAN HARDY |
| Address approval | Cleared | 2/23/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/23/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/26/2024 | JEANIE LAM |
Contact Information
| Contractor | Ams Construction Group Inc; Lic. No.: 1011558-B | 6429 WELLOUGHBY AVENUE LOS ANGELES, CA 90038 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/17/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/15/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 8/15/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/15/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 8/15/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 8/15/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/11/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/11/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/11/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 9/11/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 9/13/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/13/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 9/16/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 9/17/2024 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 11/21/2024 | Corrections Issued | JOSH MEISTER |
| Special/Order Compliance | 11/25/2024 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 11/25/2024 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| METHANE-Final | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Smoke Detectors | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/30/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 5/30/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/5/2025 | Approved | JUSTIN HAWLEY |
| Final | 6/5/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 6/5/2025 | Approved | JUSTIN HAWLEY |