1615 N RAVENNA AVE 90744

Certificate Information: 1615 N RAVENNA AVE 90744

Application / Permit
23014-10000-03967
Plan Check / Job No.
B23LA18209
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
COVERED PATIO ON FIRST FLOOR ATTACHED TO EXISTING GARAGE (portion of garage to be demo'd). ADU ON SECOND FLOOR PER 12.22A.33(c) and (d)
Permit Issued
Issued on 7/26/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 MARCELA FRANQUEZ
Corrections Issued 10/20/2023 MARCELA FRANQUEZ
Quality Review Completed 10/27/2023 KEN GILL
Building Plans Picked Up 11/2/2023 APPLICANT
Plan Check Approved 7/17/2024 MARCELA FRANQUEZ
Issued 7/26/2024 APPLICANT
CofO in Progress 8/29/2025 EUGENE CASSIDY
CofO Issued 9/4/2025 ANSON MAGLASANG
Permit Finaled 9/4/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/8/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/9/2024 ERIK BEASLEY
Sewer availability Cleared 1/9/2024 ERIK BEASLEY
Clean Up Green Up Cleared 1/11/2024 RUBEN VASQUEZ
Low Impact Development (LID) Cleared 3/5/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/7/2024 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/1/2024 No Result Entered BOB GOBUTY
PLUMBING-Rough 10/2/2024 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/8/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/8/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 1/17/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 1/17/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 1/17/2025 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 1/23/2025 Conditional Approval EUGENE CASSIDY
METHANE-Barrier 1/23/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 1/23/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/11/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/11/2025 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/11/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 3/11/2025 Corrections Issued EUGENE CASSIDY
METHANE-Rough 3/11/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/11/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 3/19/2025 Approved EUGENE CASSIDY
HVAC-Rough 3/19/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 3/19/2025 Approved EUGENE CASSIDY
Insulation 3/26/2025 Approved EUGENE CASSIDY
Shower Pan 3/26/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/3/2025 Approved EUGENE CASSIDY
Drywall Nailing 4/3/2025 Approved EUGENE CASSIDY
Green Building Rough 4/3/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/3/2025 Approved EUGENE CASSIDY
METHANE-Rough 4/3/2025 Approved EUGENE CASSIDY
Sewer 4/3/2025 Approved EUGENE CASSIDY
Underground Mechanical 4/3/2025 Partial Approval EUGENE CASSIDY
Underground Mechanical 5/30/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Final 8/1/2025 Not Ready for Inspection EUGENE CASSIDY
Final 8/1/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/1/2025 Approved EUGENE CASSIDY
Green Building Final 8/1/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 8/1/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 8/1/2025 Approved EUGENE CASSIDY
PLUMBING-Final 8/1/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 8/1/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/22/2025 Not Ready for Inspection EUGENE CASSIDY
Final 8/22/2025 Corrections Issued EUGENE CASSIDY
Gas Test 8/22/2025 Approved EUGENE CASSIDY
Green Building Final 8/22/2025 Approved EUGENE CASSIDY
HVAC-Final 8/22/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 8/22/2025 Approved EUGENE CASSIDY
Service/Power Release 8/22/2025 Not Required EUGENE CASSIDY
Smoke Detectors 8/22/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/29/2025 Approved EUGENE CASSIDY
Final 8/29/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/29/2025 Approved EUGENE CASSIDY
PLUMBING-Final 8/29/2025 Approved EUGENE CASSIDY
Service/Power Release 8/29/2025 Not Required EUGENE CASSIDY