4708 N NOBLE AVE 91403

Certificate Information: 4708 N NOBLE AVE 91403

Application / Permit
23014-10000-03958
Plan Check / Job No.
B23LA18164
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan MAJOR REMODEL AND ADDITION TO (E) 1 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE. DEMO 99% OF EXISTING DWELLING AND LEAVE 2 FEET OF WALL WITH FOOTING. PROPOSED STRUCTURE TO BECOME TWO STORY SINGLE FAMILY DWELLING WITH ATTAHCED 2-CAR GARAGE WITH OPEN BALCONY AND OPEN DECK ON SECOND FLOOR NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 2/24/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 JAD BASMA
Corrections Issued 10/7/2023 JAD BASMA
Quality Review Completed 10/11/2023 GARO TELMI
Applicant returned to address corrections 1/16/2024 JAD BASMA
Plan Check Approved 2/21/2024 JAD BASMA
Issued 2/24/2024 APPLICANT
CofO in Progress 1/30/2025 JACK KARGODORIAN
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2023 CARLOS AGUILERA
Sewer availability Cleared 10/19/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/15/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 12/5/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/5/2023 CARLOS AGUILERA
Trees in Parkway Cleared 2/15/2024 ADALBERTO VERA
Permit Cleared 2/16/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/29/2024 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 4/17/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/17/2024 Approved THOMAS FINNILA
Deputy Reinf. Concrete 4/18/2024 Conditional Approval DAVID MATSON
Wood Frame 4/29/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval THOMAS FINNILA
Wood Frame 5/2/2024 Partial Approval THOMAS FINNILA
Special/Order Compliance 5/16/2024 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 5/28/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 5/28/2024 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 5/28/2024 Approved JACK KARGODORIAN
HVAC-Rough 5/28/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/28/2024 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 5/30/2024 Approved JACK KARGODORIAN
Gas Test 5/30/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/30/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/5/2024 Approved MICHEL ABAJAN
Shower Pan 6/5/2024 Approved MICHEL ABAJAN
Insulation 6/6/2024 Approved GREGG CUMMINGS
Drywall Nailing 6/10/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/10/2024 Approved JACK KARGODORIAN
HVAC-Final 9/5/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 9/5/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 9/9/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 9/9/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 9/10/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/13/2024 Approved JACK KARGODORIAN
Final 9/13/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 9/13/2024 Approved JACK KARGODORIAN
HVAC-Final 9/13/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/13/2024 Approved JACK KARGODORIAN
Final 1/30/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 1/30/2025 Approved JACK KARGODORIAN