120 S MAPLETON DR 90024
Certificate Information: 120 S MAPLETON DR 90024
- Application / Permit
- 23014-10000-03956
- Plan Check / Job No.
- B23LA18161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Remodel of (E) SFD INTERIOR RENOVATION AND 2 STORY ADDITION TO EXISTING MAIN DWELLLING.
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Current Status
- Issued on 10/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 10/17/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/19/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/13/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/28/2024 | ARSALAN SHABESTARI |
| Issued | 10/30/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/24/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 1/17/2024 | PEDRO AYALA |
| ZA Case | Cleared | 5/13/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 5/17/2024 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 9/5/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/24/2024 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 10/28/2024 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 10/28/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Clear Construction Inc; Lic. No.: 999874-B | , |
| Engineer | Judd,, Shane Dennis; Lic. No.: NA70991 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2026 |
Inspection Request History
| Pre-Inspection | 1/10/2025 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Corrections Issued | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 7/15/2025 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 8/7/2025 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/6/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 12/18/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/10/2026 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 2/24/2026 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/6/2026 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 3/18/2026 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 3/18/2026 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/8/2026 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/21/2026 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/28/2026 | Partial Approval | DAVID SCANTLIN |