8723-8725 S BLERIOT AVE 90045

Certificate Information: 8723-8725 S BLERIOT AVE 90045

Application / Permit
23014-10000-03953
Plan Check / Job No.
B23LA18153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition ADU at existing SFD w/ attached garage
Permit Issued
Issued on 5/28/2024
Issuing Office
Current Status
Issued on 5/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 JOE VO
Corrections Issued 10/8/2023 JOE VO
Quality Review Completed 10/12/2023 GARO TELMI
Plan Check Approved 5/21/2024 JOE VO
Issued 5/28/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/16/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/17/2023 DARIN LAM
Sewer availability Cleared 10/17/2023 DARIN LAM
Specific Plan Cleared 10/25/2023 ALESSANDRO MERCURI
Hydrant and Access approval Cleared 11/17/2023 KURT CORRAL
Low Impact Development (LID) Cleared 2/13/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/15/2024 LIAM ODONOVAN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 6/5/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 6/6/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Partial Approval BOBBY KEY
HVAC-Rough 6/26/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 6/26/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Corrections Issued BOBBY KEY
Special/Order Compliance 9/18/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 9/20/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 9/20/2024 Corrections Issued JESUS PINEDA
Green Building Rough 9/20/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 9/20/2024 Approved JESUS PINEDA
PLUMBING-Rough 9/20/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 9/25/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 11/20/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/13/2024 Approved TEMISTOCLES CAAL
Green Building Rough 12/13/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 12/13/2024 Partial Approval TEMISTOCLES CAAL
Shower Pan 12/13/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 12/13/2024 Partial Inspection JAYLIN GRAVITTE
Insulation 12/19/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 12/23/2024 Partial Approval EVAN COOPER
Drywall Nailing 12/24/2024 Approved BOBBY KEY
Interior/Exterior Lathing 12/24/2024 Approved BOBBY KEY
ELECTRICAL-Final 8/26/2025 Corrections Issued JESUS PINEDA
Final 8/26/2025 Corrections Issued JESUS PINEDA
Green Building Final 8/26/2025 Corrections Issued JESUS PINEDA
HVAC-Final 8/26/2025 Approved JESUS PINEDA
PLUMBING-Final 8/26/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 8/26/2025 Approved JESUS PINEDA