2268 W HILL DR 90041
Certificate Information: 2268 W HILL DR 90041
- Application / Permit
- 23014-10000-03942
- Plan Check / Job No.
- B23LA18073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8'-11.5" X 6'-7" ADDITION AND REMODEL TO THE SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/3/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/11/2023 | DANIEL ABRAMYAN |
| Issued | 10/23/2023 | APPLICANT |
| CofO in Progress | 8/29/2024 | CRAIG VAUGHAN |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/4/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 10/4/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | JESSICA OPINION |
| Grading Pre-Inspection | Cleared | 10/11/2023 | GIOVANNY CHAVEZ |
Contact Information
| Contractor | Hartman Baldwin Inc; Lic. No.: 653340-B | , |
| Engineer | Mutka,, Jason Richard; Lic. No.: NA72255 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 1/16/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/14/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 2/14/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/14/2024 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/14/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 2/20/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Insulation | 2/22/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/28/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 3/15/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/2/2024 | Approved | CRAIG VAUGHAN |
| Shower Pan | 4/2/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/24/2024 | Approved | BRIAN SULLIVAN |
| Final | 6/24/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 6/24/2024 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 6/24/2024 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 6/24/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/24/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/12/2024 | Approved | CRAIG VAUGHAN |
| Final | 8/12/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 8/12/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 8/12/2024 | Approved | CRAIG VAUGHAN |
| Final | 8/28/2024 | OK to Issue CofO | CRAIG VAUGHAN |