1616 W 221ST ST 90501

Certificate Information: 1616 W 221ST ST 90501

Application / Permit
23014-10000-03918
Plan Check / Job No.
B23LA17980
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan-NEW 1ST AND 2ND FLOOR ADDITON TO (E) 1-STORY SFD WITH ATTACHED GARAGE WITH INTERIOR AND EXTERIOR STR. REMODEL - ENTIRE BLDG IS EQUIPPED WITH SPRINKLER
Permit Issued
Issued on 7/22/2024
Issuing Office
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 MAHNAZ NOURHASHEMI
Corrections Issued 10/20/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 11/3/2023 TU HUA
Applicant returned to address corrections 5/14/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 5/20/2024 MAHNAZ NOURHASHEMI
Issued 7/22/2024 APPLICANT
CofO in Progress 11/25/2025 EUGENE CASSIDY
Permit Finaled 11/25/2025 ANSON MAGLASANG
Permit Finaled 11/25/2025 ANSON MAGLASANG
CofO Issued 11/25/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/28/2023 KHAING AYE
Low Impact Development (LID) Cleared 2/28/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/6/2024 ERIK BEASLEY
Sewer availability Cleared 3/13/2024 KHAING AYE

Contact Information

Contractor Liel Construction Inc; Lic. No.: 929105-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/7/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 8/9/2024 Partial Approval EUGENE CASSIDY
METHANE-Barrier 8/9/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 8/9/2024 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 8/23/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 8/26/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 8/26/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Partial Approval EUGENE CASSIDY
Insulation 9/3/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 10/30/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 10/30/2024 Approved EUGENE CASSIDY
Green Building Rough 10/30/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 10/30/2024 Approved EUGENE CASSIDY
METHANE-Rough 10/30/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 10/30/2024 Approved EUGENE CASSIDY
Deputy Wood Construction 11/13/2024 Conditional Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Partial Approval EUGENE CASSIDY
Wood Frame 11/15/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/11/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/23/2025 Approved EUGENE CASSIDY
Green Building Rough 1/23/2025 Approved EUGENE CASSIDY
Insulation 1/23/2025 Approved EUGENE CASSIDY
Drywall Nailing 1/28/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/5/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Not Ready EUGENE CASSIDY
ELECTRICAL-Final 6/30/2025 Approved ANTHONY EGSON
Final 6/30/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 6/30/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 6/30/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved ANTHONY EGSON
Final 10/15/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 10/15/2025 Approved EUGENE CASSIDY
Smoke Detectors 10/15/2025 Approved EUGENE CASSIDY
Final 11/24/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/24/2025 Approved EUGENE CASSIDY