807 E CRESTMOORE PL 90291
Certificate Information: 807 E CRESTMOORE PL 90291
- Application / Permit
- 23014-10000-03913
- Plan Check / Job No.
- B23LA17963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: TWO IRREGLAR SHAPED ADDITIONS TO FRONT TOTAL OF (150 SF ) AND 22 SF FRONT PORCH ADDITION TO AN EXISTING 2-STORY DUPLEX. ALL WORK PER ENG.
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 9/30/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/19/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/3/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/6/2023 | LUISANGEL VALENZUELA |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 1/28/2025 | JESUS PINEDA |
| Permit Finaled | 1/30/2025 | RICHARD STEINBACH |
| CofO Issued | 1/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/2/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2023 | DARIN LAM |
| Miscellaneous | Cleared | 10/5/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 10/5/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 10/5/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 10/5/2023 | SPENCER WEJROWSKI |
| Specific Plan | Cleared | 11/27/2023 | LUIS LOPEZ |
| ZI | Cleared | 11/27/2023 | LUIS LOPEZ |
| Coastal Zone | Cleared | 11/28/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: NA87698 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/8/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/20/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 8/9/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/25/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/4/2024 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 10/4/2024 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 10/10/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 10/10/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 10/10/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/10/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/10/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/16/2024 | Approved | JESUS PINEDA |
| Insulation | 10/16/2024 | Approved | JESUS PINEDA |
| Special/Order Compliance | 10/16/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 10/22/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 1/6/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 1/6/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 1/6/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 1/28/2025 | Approved | JESUS PINEDA |
| Final | 1/28/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 1/28/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 1/28/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 1/28/2025 | Approved | JESUS PINEDA |