1071 N KENTER AVE 90049

Certificate Information: 1071 N KENTER AVE 90049

Application / Permit
23014-10000-03888
Plan Check / Job No.
B23LA17873
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) KITCHEN REMODEL WHICH INCLUDES THE DEMOLITION OF (2) EXISTING WALLS AND THE ADDITION OF 13 SF BY CONVERTING A PORTION OF THE EXISTING CRAWL SPACE INTO A WALK-IN PANTRY. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 11/13/2023
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2023 APPLICANT
Assigned to Plan Check Engineer 9/27/2023 FERNANDO FLORES
Corrections Issued 9/28/2023 FERNANDO FLORES
Applicant returned to address corrections 10/12/2023 OMAR GARNICA
Applicant returned to address corrections 10/18/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/7/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 11/9/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 11/13/2023 MIROOSH KHACHATOORIAN
Issued 11/13/2023 APPLICANT
CofO in Progress 10/25/2024 ARAM AVEDISIAN
CofO Issued 10/30/2024 RICHARD STEINBACH
Permit Finaled 10/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/8/2023 VASIL MIHALEV

Contact Information

Architect Larue,, Jordan; Lic. No.: C37045 1234 N KENMORE AVE      LOS ANGELES, CA 90029
Contractor Owner-Builder       ,
Engineer Vasquez,, Mario A; Lic. No.: C89006 1942 SPANISH BROOM DR      PALMDALE, CA 93550

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/9/2024 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/9/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/9/2024 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 5/15/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 5/31/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 5/31/2024 Approved KEVIN SARGSYAN
Green Building Rough 5/31/2024 Approved KEVIN SARGSYAN
HVAC-Rough 5/31/2024 Approved KEVIN SARGSYAN
PLUMBING-Rough 5/31/2024 Approved KEVIN SARGSYAN
Drywall Nailing 6/4/2024 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 6/6/2024 Approved KEVIN SARGSYAN
Final 9/20/2024 No Access for Inspection KEVIN SARGSYAN
Green Building Final 9/20/2024 No Access for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/20/2024 No Access for Inspection KEVIN SARGSYAN
Smoke Detectors 9/20/2024 No Access for Inspection KEVIN SARGSYAN
Final 10/16/2024 Corrections Issued KEVIN SARGSYAN
Green Building Final 10/16/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 10/16/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/25/2024 Approved ARAM AVEDISIAN
Final 10/25/2024 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 10/25/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 10/25/2024 Approved ARAM AVEDISIAN