1305 N HIGHGATE AVE 90042

Certificate Information: 1305 N HIGHGATE AVE 90042

Application / Permit
23014-10000-03882
Plan Check / Job No.
B23LA17857
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 24'-6" X 10'-9" ADDITION TO (E) SFD, ALL WORK PER ENG.
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
Issued on 10/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2023 APPLICANT
Assigned to Plan Check Engineer 9/29/2023 LUISANGEL VALENZUELA
Corrections Issued 9/30/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/11/2023 LUISANGEL VALENZUELA
Plan Check Approved 10/17/2023 LUISANGEL VALENZUELA
Issued 10/18/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 10/5/2023 JEANIE LAM
Sewer availability Cleared 10/5/2023 JEANIE LAM
Grading Pre-Inspection Cleared 10/11/2023 LUISANGEL VALENZUELA

Contact Information

Contractor Prime Construction; Lic. No.: 1031676-B       ,
Contractor Your Prime Contractor Inc; Lic. No.: 1031676-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/30/2023 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 No Access for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/20/2023 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 12/13/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 12/13/2023 Not Ready for Inspection ROY SPAULDING
Wood Frame 12/13/2023 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 1/22/2024 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 1/22/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 1/22/2024 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 2/2/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 2/2/2024 Approved ROY SPAULDING
PLUMBING-Rough 2/2/2024 Corrections Issued ROY SPAULDING
PLUMBING-Rough 2/14/2024 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 2/14/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/27/2024 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/27/2024 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 2/27/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/13/2024 Approved LILIANA PORTILLO
Insulation 3/13/2024 Corrections Issued LILIANA PORTILLO
Drywall Nailing 3/21/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/26/2024 Partial Approval ALIZAH MAYAGOITIA