8350 S NAYLOR AVE 90045
Certificate Information: 8350 S NAYLOR AVE 90045
- Application / Permit
- 23014-10000-03851
- Plan Check / Job No.
- B23LA17780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Addtion and conversion of existing attached carport to storage attached to existing 1 story detached garage per WFPP.
- Permit Issued
- Issued on 12/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | AUNG SOE |
| Corrections Issued | 10/3/2023 | AUNG SOE |
| Building Plans Picked Up | 10/11/2023 | APPLICANT |
| Plan Check Approved | 12/20/2023 | YAQUB MIRZA |
| Issued | 12/20/2023 | APPLICANT |
| CofO in Progress | 4/29/2024 | RICHARD STEINBACH |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
| CofO Issued | 4/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 10/10/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/10/2023 | DARIN LAM |
| Specific Plan | Cleared | 10/14/2023 | EDUARDO HERMOSO |
| Construction near power lines | Cleared | 12/15/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 12/15/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | A M F Construction; Lic. No.: 1077878-B | 13428 MAXELLA AVE #786 MARINA DEL REY, CA 90292 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/29/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 1/29/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/8/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | BOBBY KEY |
| Final | 4/11/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/11/2024 | Approved | BOBBY KEY |
| Green Building Rough | 4/11/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 4/11/2024 | Corrections Issued | BOBBY KEY |
| Final | 4/26/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 4/26/2024 | Approved | TEMISTOCLES CAAL |