3599 1/4 E LOMA LADA DR 90065

Certificate Information: 3599 1/4 E LOMA LADA DR 90065

Application / Permit
23014-10000-03845
Plan Check / Job No.
B23LA17753
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED GARAGE CONVERSION TO A J/ADU - 448 SF JADU CHECKED PER CA GOVT. CODE 65852.2(E)(1)(A) AND 65852.22
Permit Issued
Issued on 5/31/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 SUNMIN LEE
Corrections Issued 10/10/2023 SUNMIN LEE
Quality Review Completed 10/20/2023 KEN GILL
Building Plans Picked Up 10/26/2023 APPLICANT
Plan Check Approved 5/20/2024 SUNMIN LEE
Issued 5/31/2024 APPLICANT
CofO in Progress 2/19/2025 THOMAS LOGRASSO
Permit Finaled 2/20/2025 DEROLD HAUFF
CofO Issued 2/20/2025 DEROLD HAUFF
Permit Finaled 2/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/27/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/31/2023 CHRISTINA BRACO
Permit Cleared 10/31/2023 CHRISTINA BRACO
Specific Plan Cleared 2/27/2024 PABLO ESTRADA
BHO/Hillside ordinance Cleared 4/24/2024 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 4/24/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 4/24/2024 CHRISTINA BRACO
Grading Pre-Inspection Cleared 5/20/2024 SUNMIN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Haro,, Ruben; Lic. No.: C72213 899 PIERCE COURT      THOUSAND OAKS, CA 91360
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/22/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 8/28/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 8/28/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/8/2024 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 10/8/2024 Approved THOMAS LOGRASSO
HVAC-Rough 10/8/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 10/8/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 10/8/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/15/2024 Approved THOMAS LOGRASSO
HVAC-Rough 10/15/2024 Approved THOMAS LOGRASSO
Insulation 10/15/2024 Approved THOMAS LOGRASSO
Drywall Nailing 10/21/2024 Approved THOMAS LOGRASSO
Shower Pan 10/29/2024 Approved ROY SPAULDING
Final 1/7/2025 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 1/7/2025 Approved THOMAS LOGRASSO
Final 2/4/2025 Not Ready for Inspection THOMAS LOGRASSO
Final 2/19/2025 OK to Issue CofO THOMAS LOGRASSO