5723 W 75TH ST 90045
Certificate Information: 5723 W 75TH ST 90045
- Application / Permit
- 23014-10000-03839
- Plan Check / Job No.
- B23LA17716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. ADDITON TO (E) SFD
- Permit Issued
- Issued on 2/20/2024
- Issuing Office
- Current Status
- Issued on 2/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/25/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/10/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/14/2024 | MOHAMMAD ESMAILI |
| Issued | 2/20/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 1/29/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/30/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2024 | LIAM ODONOVAN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/29/2024 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 3/7/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/11/2024 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 3/26/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/26/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/9/2024 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/9/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/9/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 5/9/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/14/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 5/14/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/14/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/16/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 5/16/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/16/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/30/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 5/30/2024 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 5/30/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | BOBBY KEY |
| MERV13>=Rough | 5/30/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 5/30/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 6/20/2024 | Approved | BOBBY KEY |
| Green Building Rough | 6/20/2024 | Approved | BOBBY KEY |
| Insulation | 6/20/2024 | Approved | BOBBY KEY |
| MERV13>=Rough | 6/20/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/20/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 7/10/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/10/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 12/17/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 12/17/2024 | Approved | TEMISTOCLES CAAL |
| Final | 6/10/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 6/10/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 6/10/2025 | Approved | JESUS PINEDA |
| MERV13>=Final | 6/10/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 6/10/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 6/10/2025 | Approved | JESUS PINEDA |