631 1/2 E 83RD ST 90001
Certificate Information: 631 1/2 E 83RD ST 90001
- Application / Permit
- 23014-10000-03823
- Plan Check / Job No.
- B23LA17647
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert the (E) Garage to be ADU with (N) secound floor addition to be part of ADU resolting into two story ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | GEORGE JOLAKIAN |
| Corrections Issued | 10/13/2023 | GEORGE JOLAKIAN |
| Quality Review Completed | 10/20/2023 | KEN GILL |
| Building Plans Picked Up | 11/15/2023 | APPLICANT |
| Plan Check Approved | 4/26/2024 | GEORGE JOLAKIAN |
| Issued | 4/26/2024 | APPLICANT |
| CofO in Progress | 5/1/2025 | JOHN QUINTANILLA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/6/2024 | RIDWAN HARDY |
| Address approval | Cleared | 4/2/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 4/2/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 4/8/2024 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/1/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/1/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 9/13/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/13/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/21/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 10/21/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/21/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/24/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/24/2024 | Approved | MICHAEL LEWIS |
| Insulation | 10/28/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/30/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | JOSH MEISTER |
| Final | 12/24/2024 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 12/24/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 12/24/2024 | Approved | JOHN QUINTANILLA |
| Final | 1/17/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 1/17/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 4/21/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 4/28/2025 | OK to Issue CofO | JOHN QUINTANILLA |