228 1/2 W 111TH ST 90061

Certificate Information: 228 1/2 W 111TH ST 90061

Application / Permit
23014-10000-03803
Plan Check / Job No.
B23LA17577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT. NEW 8'-6" x 18'-3" ADDITION TO THE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). WORK DONE PER WFPP.
Permit Issued
Issued on 10/20/2023
Issuing Office
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 GIOVANNY CHAVEZ
Corrections Issued 9/25/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 10/5/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 10/12/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 10/16/2023 DANIEL ABRAMYAN
Plan Check Approved 10/17/2023 DANIEL ABRAMYAN
Issued 10/20/2023 APPLICANT
CofO in Progress 3/11/2024 JAMES CHAVEZ
CofO in Progress 3/11/2024 JAMES CHAVEZ
CofO in Progress 3/12/2024 JAMES CHAVEZ
Permit Finaled 3/12/2024 ANSON MAGLASANG
CofO Issued 3/12/2024 ANSON MAGLASANG
Permit Finaled 3/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/30/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/30/2023 CHRISTINA BRACO
Sewer availability Cleared 9/30/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/3/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/16/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 12/6/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 12/11/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/8/2024 Approved JOHN KLARIN
HVAC-Rough 1/8/2024 Corrections Issued JOHN KLARIN
PLUMBING-Rough 1/8/2024 Approved JOHN KLARIN
HVAC-Rough 1/11/2024 Approved JOHN KLARIN
Shower Pan 1/11/2024 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 1/18/2024 Approved JOHN KLARIN
Insulation 1/18/2024 Approved JOHN KLARIN
Interior/Exterior Lathing 1/18/2024 Corrections Issued JOHN KLARIN
Shower Pan 1/18/2024 Approved JOHN KLARIN
Drywall Nailing 1/24/2024 Partial Approval JAMES CHAVEZ
Interior/Exterior Lathing 1/24/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/29/2024 Approved JAMES CHAVEZ
Drywall Nailing 2/29/2024 Approved JAMES CHAVEZ
Final 2/29/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 2/29/2024 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 2/29/2024 Approved JAMES CHAVEZ
MERV13>=Final 2/29/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 2/29/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 2/29/2024 Not Ready for Inspection JAMES CHAVEZ
Final 3/8/2024 Conditional Approval JAMES CHAVEZ
Green Building Final 3/8/2024 Approved JAMES CHAVEZ
MERV13>=Final 3/8/2024 Approved JAMES CHAVEZ
Smoke Detectors 3/8/2024 Approved JAMES CHAVEZ
Special/Order Compliance 3/11/2024 Corrections Issued JAMES CHAVEZ
Final 3/12/2024 OK to Issue CofO JAMES CHAVEZ