8343 S FLIGHT AVE 90045
Certificate Information: 8343 S FLIGHT AVE 90045
- Application / Permit
- 23014-10000-03770
- Plan Check / Job No.
- B23LA17443
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and Conversion of existing detached garage to ADUper CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 9/29/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 10/6/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 10/11/2023 | FERNANDO FLORES |
| Plan Check Approved | 1/30/2024 | NEHEMIAS RAMOS |
| Issued | 2/12/2024 | APPLICANT |
| CofO in Progress | 8/1/2024 | HERBERT GIRON |
| Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
| CofO Issued | 8/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/4/2023 | ALESSANDRO MERCURI |
| Address approval | Cleared | 10/10/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/11/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/22/2024 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 1/24/2024 | RIDWAN HARDY |
Contact Information
| Architect | , ; Lic. No.: C37124 | 1734 WILCOX AVENUE LOS ANGELES, CA 90028 |
| Contractor | Karma Remodel & Development Inc; Lic. No.: 875130-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/15/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 2/20/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 2/20/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/21/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/21/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 2/26/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/26/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 3/26/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 3/26/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/30/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/30/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/30/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/1/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 5/6/2024 | Approved | BOBBY KEY |
| Shower Pan | 5/6/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 5/6/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Insulation | 5/9/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 5/9/2024 | Approved | BOBBY KEY |
| Insulation | 5/13/2024 | Partial Approval | BOBBY KEY |
| Insulation | 5/16/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 5/20/2024 | Approved | BOBBY KEY |
| Green Building Rough | 5/20/2024 | Approved | BOBBY KEY |
| Final | 6/27/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 6/27/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/27/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 7/2/2024 | Corrections Issued | BOBBY KEY |
| Final | 7/2/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/2/2024 | Approved | BOBBY KEY |
| HVAC-Final | 7/2/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/2/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/2/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/30/2024 | Approved | HERBERT GIRON |
| Final | 7/30/2024 | OK to Issue CofO | HERBERT GIRON |